Sydney Children's Hospital Stage 1 and Children’s Comprehensive Cancer Centre

Decided: approved on 17 Dec 2021Health

Where it is in the process

Approved on 17 Dec 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination17 Dec 2021 (done)
  9. Approved17 Dec 2021

What it proposes

The department's description

Construction and use of a new 12 storey hospital building (including two basement levels and upper plant room) for the Sydney Children’s Hospital and Children’s Comprehensive Cancer Centre.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

12 submissions: 3 from the public and 9 from public authorities

Object0
Support1
Comment11

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

6 changes to the project after its decision, each assessed as a case of its own, newest first.

SCH and CCCC MOD 6 - Changes to GTP conditionsSSD-10831778-Mod-6

Decided: approved on 29 Oct 2025 by the department (team leader)

Amendments to the conditions relating to the requirement for a Green Travel Plan, landscaping maintenance and bicycle parking access.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

SCH and CCCC MOD 5 - Landscaping changesSSD-10831778-Mod-5

Decided: approved on 7 Mar 2025 by the department (director)

Minor modifications to the design and landscaping of the ground floor outdoor area, including changes to the playground, pedestrian stairs and ramp. Changes to the number of skylights is also proposed.

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Modification 4 Minor Signage and Plant ChangesSSD-10831778-Mod-4

Decided: approved on 22 Mar 2024 by the department (team leader)

Minor alterations to the signage strategy and reconfiguration of building plant located at Basement Level 02, Level 09 and Level 10.

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

SCH and CCCC MOD 3 - Design changesSSD-10831778-Mod-3

Decided: approved on 20 Sep 2023 by the department (team leader)

Minor design changes comprising: modified landscaping at Level 06 courtyards; extended link bridge to the ASB; and addition of ventilation flues for plant on the roof.

Its 13 documents

13 documents in 4 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

SCH and CCCC MOD 2 - Design changesSSD-10831778-Mod-2

Decided: approved on 18 Apr 2023 by the department (team leader)

Reduce the width of the link bridge to the adjacent Health Translation Hub building and expand the floor space of the Level 02 (pharmacy) and Level 03 (Starlight Foundation), and associated facade changes.

Its 11 documents

11 documents in 3 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

SCH and CCCC MOD 1 - Design changesSSD-10831778-Mod-1

Decided: approved on 30 Nov 2022 by the department (team leader)

Expansion of the Emergency Department (ED) footprint on Basement Level 1 by approximately 218sqm, and amend the approved roof form from a pitched steel roof to a flat concrete roof form and include photovoltaic cells.

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.