On the map
State significant development

Suntop Solar Farm

Decided: approved on 4 Dec 2018Other

Where it is in the process

Approved on 4 Dec 2018

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination4 Dec 2018 (done)
  9. Approved4 Dec 2018

What it proposes

The department's description

Development of a 170 MW solar farm and associated infrastructure. Project website: https://suntopsolarfarm.com.au/

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 1 from the public and 8 from organisations

Object0
Support0
Comment9

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Suntop Solar Mod 2 - Battery Storage SystemSSD-8696-Mod-2

Under way: at prepare mod report

Development of a 200 MW / 800 MWh battery storage system and ancillary infrastructure.

Its page on the Planning Portal

MOD 1 - Substation location and layoutSSD-8696-Mod-1

Decided: approved on 11 Oct 2019 by the department (director)

- Relocation of the substation - Increased landscaping along the western boundary - Amending the approved subdivision plan to reflect the relocation of the substation and creating an access easement for the substation.

Its 14 documents

14 documents in 4 folders, each on the NSW Planning Portal

Modification Application10

See the 10 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.