Apsley Battery Energy Storage System

Decided: approved on 2 Jun 2023Energy: batteriesDistrict scale

Where it is in the process

Approved on 2 Jun 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination2 Jun 2023 (done)
  9. Approved2 Jun 2023

What it proposes

The department's description

Development of a 120 MW / 240 MWh battery energy storage facility with associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1 submission: 1 from public authorities

Object0
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Apsley BESS Modification 1SSD-35160796-Mod-1

Under way: at assessment · 4 submissions

Increase in BESS capacity, increase in construction period including workers and water requirements, increase in vehicle movements including OSOM and amendments to the development footprint and site access.

Its 40 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.