A 200 MW battery at 1 McIntosh Drive, Mayfield West

Decided: approved on 23 Mar 2026Energy: batteriesDistrict scale

Where it is in the process

Approved on 23 Mar 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination23 Mar 2026 (done)
  9. Approved23 Mar 2026

What it proposes

AI summary. Written from this project's page and its Development consent and Steel River East BESS_Assessment Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 200 MW battery at 1 McIntosh Drive, Mayfield West

The project is a battery energy storage system with a capacity of 200 MW / 400 MWh at 1 McIntosh Drive, Mayfield West, in the City of Newcastle. It would sit within an existing electricity substation site, about 7 km north-west of Newcastle, in an industrial estate. Construction would take 18 to 21 months and employ up to 100 people. The department gives an estimated development cost of $208 million and 1 operational job.

The environmental impact statement (EIS) was exhibited from 2 Jun 2025 to 30 Jun 2025 and drew 66 submissions: 62 objecting and 4 supporting. The proponent responded in a submissions report and gave more information, making minor layout changes. The department's assessment report of February 2026 found the project approvable subject to conditions. The Independent Planning Commission approved it on 23 Mar 2026. Next, the proponent must meet the consent's conditions, including a voluntary planning agreement with the council, before construction.

Capital investment
$208MSteel River East BESS_Assessment Report
Battery power capacity
200 MWSteel River East BESS_Assessment Report
Battery storage capacity
400 MWhSteel River East BESS_Assessment Report
Construction jobs
100 jobsSteel River East BESS_Assessment Report
Operational jobs
1 jobsSteel River East BESS_Assessment Report
Site area
5.06 haSteel River East BESS_Assessment Report
Development footprint
2.74 haSteel River East BESS_Assessment Report

The department's description

Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 200MW/400MWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

66 submissions: 56 from the public, 9 from organisations and 1 from public authorities

Object62
Support4
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

81 documents in 11 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS14
Response to Submissions7
Agency Advice27
Additional Information16
Recommendation3
Determination2
Management Plans and Strategies8
Other Documents1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.