On the map
Part 3A project

St Ives Residential

Decided: approved on 2 May 2011Homes

Where it is in the process

Approved on 2 May 2011

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination2 May 2011 (done)
  10. Approved2 May 2011

What it proposes

The portal gives no description.

Modifications

9 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 9 - Fire System CabinetMP10_0057-Mod-9

Decided: approved on 28 Feb 2013 by the department (executive director)

Its 6 documents

6 documents in 2 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 7 - Subdivision AmendementsMP10_0057-Mod-7

Decided: approved on 17 Sep 2012 by the department (deputy director-general)

Its 19 documents

19 documents in 4 folders, each on the NSW Planning Portal

Application9

See the 9 documents on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 8 - Changes to Unit 449MP10_0057-Mod-8

Decided: approved on 30 Aug 2012 by the department (deputy director-general)

Its 8 documents

8 documents in 2 folders, each on the NSW Planning Portal

Application5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 6 - Pergolas AdditionsMP10_0057-Mod-6

Decided: approved on 23 May 2012 by the department (executive director)

Its 19 documents

19 documents in 4 folders, each on the NSW Planning Portal

Application8

See the 8 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Response to Submissions6

See the 6 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Its page on the Planning Portal

Mod 5- Changes to Monastery BuildingMP10_0057-Mod-5

Decided: approved on 29 Feb 2012 by the Independent Planning Commission

Its 26 documents

Its page on the Planning Portal

Mod 4 - Rooftop AmendmentsMP10_0057-Mod-4

Decided: approved on 20 Feb 2012 by the Independent Planning Commission

Its 85 documents

Its page on the Planning Portal

Mod 3- Car ParkingMP10_0057-Mod-3

Decided: disapproved on 8 Dec 2011 by the Independent Planning Commission

Its 18 documents

Its page on the Planning Portal

Mod 2- Basement DewateringMP10_0057-Mod-2

Decided: approved on 2 Dec 2011 by the department (deputy director-general)

Its 15 documents

15 documents in 4 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Submissions6

See the 6 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - Construction AccessMP10_0057-Mod-1

Decided: approved on 17 Oct 2011 by the department (director-general)

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application5

See the 5 documents on the Planning Portal

Submissions2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.