SCEGGS Darlinghurst Concept and Stage 1

Decided: approved on 22 May 2020Education

Where it is in the process

Approved on 22 May 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination22 May 2020 (done)
  9. Approved22 May 2020

What it proposes

The department's description

Concept DA for the demolition of existing buildings, three new building envelopes for use as education establishment and child care facility, on-site vehicular drop-off, and first stage demolition of Wilkinson House and construction of one building

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

117 submissions: 109 from the public, 1 from organisations and 7 from public authorities

Object108
Support0
Comment9

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

SCEGGS Darlinghurst MOD 4 - Lift shaft increaseSSD-8993-Mod-4

Decided: approved on 20 Oct 2023 by the department (team leader) · 1 submission

Height of Lift shaft increased by 300mm

Its 16 documents

16 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

SCEGGS Darlinghurst MOD 3 - Envelope, landscapeSSD-8993-Mod-3

Decided: approved on 3 Jun 2022 by the department (director) · 7 submissions

Modifications to the approved Concept Proposal for SCEGGS Darlinghurst including: - amendments to the Wilkinson House building envelope; - revisions to the Concept Landscape Masterplan; and - amended road safety requirements.

Its 26 documents

26 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application8

See the 8 documents on the Planning Portal

Response to Submissions4

See the 4 documents on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

SCEGGS Darlinghurst MOD 2 - Heritage ConservationSSD-8993-Mod-2

Decided: approved on 6 Jul 2021 by the department (executive director)

Proposed amendment to Condition A13 to prepare the Heritage Conservation Management Plan for the site in stages.

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

SCEGGS Darlinghurst MOD 1 - Admin correctionsSSD-8993-Mod-1

Decided: approved on 15 Jan 2021 by the department (director)

administrative corrections for conditions of consent

Its 6 documents

6 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.