Decided: approved on 26 Sep 2023Health

Where it is in the process

Approved on 26 Sep 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination26 Sep 2023 (done)
  9. Approved26 Sep 2023

What it proposes

The department's description

Redevelopment of the hospital including: a new 15 storey hospital building; 3 storey extension to the east of the existing clinical services building; 2 storey vertical expansion of RPA Building 89; refurbishment works; demolition; temporary helipad.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 4 from the public, 2 from organisations and 1 from public authorities

Object2
Support3
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

RPA Redevelopment MOD 2 - Design changesSSD-47662959-Mod-2

Decided: approved on 11 Dec 2024 by the department (team leader)

Amendments including relocation and re-sizing of OSD, installation of electrical kiosk, fire booster and hardstand, changes to plant and equipment, minor internal and external alterations, changes to landscaping, ESD targets and condition wording.

Its 31 documents

31 documents in 4 folders, each on the NSW Planning Portal

Modification Application19

See the 19 documents on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

RPA Redevelopment MOD 1 - Design changesSSD-47662959-Mod-1

Decided: approved on 26 Jun 2024 by the department (team leader)

Amendments including to East Wing building facade and boundary positioning, adjustment to HLS, provision of new oxygen vessels, minor alterations to approved building envelopes, redesigned ED drop-off and landscaping.

Its 44 documents

44 documents in 4 folders, each on the NSW Planning Portal

Modification Application17

See the 17 documents on the Planning Portal

Additional Information21

See the 21 documents on the Planning Portal

Determination5

See the 5 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.