A resource recovery facility and concrete plant, Rosehill

Under way: at prepare eisWasteNeighbourhood scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Revised scoping report_19 May 2025 on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A resource recovery facility and concrete plant, Rosehill

The proponent proposes a resource recovery facility and a concrete batching plant at 12a Grand Avenue, Rosehill, in the City of Parramatta. The facility would receive, sort and recycle construction and demolition waste, with a capacity of up to 250,000 tonnes a year and storage of up to 25,000 tonnes at any one time. The concrete plant would have a capacity of 120 tonnes per hour. The site is zoned heavy industrial and was once an asphalt recycling facility. No capital investment or job numbers were read.

The case is at the stage of preparing an environmental impact statement (EIS). A revised scoping report dated 8 May 2025 was lodged with the request for the Secretary's environmental assessment requirements (SEARs), and the SEARs have been issued. No submissions have been made yet. Next, the proponent prepares the EIS, which is then exhibited so the public can make submissions. The department then assesses it.

Resource recovery facility capacity
250,000 tonnes a yearRevised scoping report_19 May 2025
Maximum waste stored at one time
25,000 tonnesRevised scoping report_19 May 2025
Concrete batching plant capacity
120 tonnes per hourRevised scoping report_19 May 2025
Concrete production
250,000 tonnes a yearPortal page

The department's description

Construction and operation of a resource recovery facility (RRF) and concrete batching plant. The RRF has a proposed capacity of 250,000 tonnes per annum. The concrete batching plant is anticipated to produce 250,000 tonnes per annum of concrete

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.