State significant development

Powerhouse Parramatta

Decided: approved on 11 Feb 2021Tourism and recreation

Where it is in the process

Approved on 11 Feb 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination11 Feb 2021 (done)
  8. Approved11 Feb 2021

What it proposes

The department's description

Site preparation works including demolition of all structures and tree removal, construction, operation and use of the Powerhouse Parramatta, public domain works and use, vehicular access, infrastructure works and signage zones

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1,686 submissions: 1,638 from the public, 39 from organisations and 9 from public authorities

Object1,613
Support40
Comment33

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Powerhouse Parramatta MOD 4 - Condition C4SSD-10416-Mod-4

Decided: approved on 20 Oct 2025 by the department (team leader)

Proposed changes to Condition C4

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Powerhouse Parramatta MOD 3 - Retail Fit-outSSD-10416-Mod-3

Decided: approved on 2 Oct 2024 by the department (team leader)

• Fit out and use of the western and eastern retail spaces • Increase in the provision of retail space associated with the cinema • Amendment to the overall gross floor area (GFA) calculation for the built form.

Its 18 documents

18 documents in 5 folders, each on the NSW Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Powerhouse Parramatta MOD 2 - HeightSSD-10416-Mod-2

Decided: approved on 19 Dec 2023 by the department (director) · 3 submissions

- increase the height of the western building from RL79.2m to RL 82.35m - design changes to the rooftop pavilion and part of the level 3 façade of the eastern building - extend Saturday construction hours from 8am to 1pm to 8am to 5pm

Its 25 documents

25 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Response to Submissions6

See the 6 documents on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Powerhouse Parramatta MOD 1 - Terrace Fit outSSD-10416-Mod-1

Decided: approved on 17 Aug 2022 by the department (team leader) · 3 submissions

4.55(1A) modification for: - fit-out and adaptive re-use of St George's Terrace to support the Powerhouse program - partial demolition of internal fabric within St George's Terrace - changes to the roof pavilion on the eastern building

Its 26 documents

26 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Response to Submissions7

See the 7 documents on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.