Where it is in the process
Approved on 11 Feb 2021
What it proposes
The department's description
Site preparation works including demolition of all structures and tree removal, construction, operation and use of the Powerhouse Parramatta, public domain works and use, vehicular access, infrastructure works and signage zones
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
1,686 submissions: 1,638 from the public, 39 from organisations and 9 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
4 changes to the project after its decision, each assessed as a case of its own, newest first.
Powerhouse Parramatta MOD 4 - Condition C4SSD-10416-Mod-4
Proposed changes to Condition C4
Its 8 documents
8 documents in 3 folders, each on the NSW Planning Portal
Modification Application5
Determination2
Consolidated Consent1
Powerhouse Parramatta MOD 3 - Retail Fit-outSSD-10416-Mod-3
• Fit out and use of the western and eastern retail spaces • Increase in the provision of retail space associated with the cinema • Amendment to the overall gross floor area (GFA) calculation for the built form.
Its 18 documents
18 documents in 5 folders, each on the NSW Planning Portal
Modification Application6
Agency Advice6
Additional Information2
Determination3
Consolidated Consent1
Powerhouse Parramatta MOD 2 - HeightSSD-10416-Mod-2
- increase the height of the western building from RL79.2m to RL 82.35m - design changes to the rooftop pavilion and part of the level 3 façade of the eastern building - extend Saturday construction hours from 8am to 1pm to 8am to 5pm
Its 25 documents
25 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application6
Response to Submissions6
Agency Advice4
Additional Information3
Determination4
Consolidated Consent1
Powerhouse Parramatta MOD 1 - Terrace Fit outSSD-10416-Mod-1
4.55(1A) modification for: - fit-out and adaptive re-use of St George's Terrace to support the Powerhouse program - partial demolition of internal fabric within St George's Terrace - changes to the roof pavilion on the eastern building
Its 26 documents
26 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application6
Response to Submissions7
Agency Advice5
Additional Information2
Determination4
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
194 documents in 13 folders, each on the NSW Planning Portal
Early Consultation1
Request for SEARs4
Response to Submissions24
Agency Advice10
Additional Information22
Determination8
Management Plans and Strategies63
Independent Reviews and Audits3
Notifications9
Other Documents11
What's near it
Its point is approximate (the register's own, to about a kilometre), and so are these.
Where it is
- Suburb
- Yengo National Park
- Council area
- Parramatta
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.