Residential development with in-fill affordable housing - Dawes Avenue, Castle Hill
80 extra homes on eight Dawes Avenue buildings, Castle Hill
Where it is in the process
Approved on 5 Dec 2025
What it proposes
AI summary. Written from this project's page and its SSD-80229956 Development Consent and Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
80 extra homes on eight Dawes Avenue buildings, Castle Hill
The project adds two storeys to eight apartment buildings approved by the Land and Environment Court at 16-30 Dawes Avenue, 2-10 Cadman Crescent and 4-8 Hughes Avenue, Castle Hill, in The Hills Shire. It would add 80 dwellings, 46 of them affordable, for a total of 360 dwellings. All buildings would be eight storeys. The estimated development cost is $179,957,157, with 500 construction jobs and 20 operational jobs.
The environmental impact statement (EIS) was exhibited from 1 Aug 2025 to 28 Aug 2025. It drew 27 public submissions: 25 objecting, 1 supporting and 1 commenting. Traffic, infrastructure capacity, building scale and amenity were raised most. The proponent amended the design to add privacy screens. The department recommended approval, and its Executive Director, as the Minister's delegate, approved it on 5 Dec 2025 with conditions. Next, the proponent must meet those conditions before construction.
- Additional dwellings
- 80 dwellingsAssessment Report
- Additional affordable dwellings
- 46 dwellingsAssessment Report
- Total dwellings
- 360 dwellingsAssessment Report
- Estimated development cost
- $180MAssessment Report
- Construction jobs
- 500 jobsAssessment Report
- Operational jobs
- 20 jobsAssessment Report
- Car parking spaces
- 631 car spacesAssessment Report
- Site area
- 15,697 m²Assessment Report
The department's description
Alterations to approved residential flat buildings (DA672/2023) involving additional floors with affordable housing.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
29 submissions: 27 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
Modification 1 Air-conditioning relocationSSD-80229956-Mod-1
Relocate roof plant and equipment
Its 12 documents
12 documents in 5 folders, each on the NSW Planning Portal
Modification Application3
Agency Advice1
Additional Information4
Determination3
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
73 documents in 12 folders, each on the NSW Planning Portal
Notice of Exhibition1
Early Consultation3
Request for SEARs2
EIS31
- Appendix 1 - Consideration of SEARs
- Appendix 10 - Survey Plan
- Appendix 11 - Preliminary Site Investigation Report
- Appendix 12 - Integrated Water Management Report
- Appendix 13 - Waste Management Plan
- Appendix 14 - BDAR Waiver Request
- Appendix 15 - BDAR Waiver
- Appendix 16 - Statutory compliance table
- Appendix 17 - Community Engagement Report
- Appendix 18 - Clause 4.6 Request - Building Height Standard
- Appendix 19 - Traffic & Parking Assessment
- Appendix 2 - Architectural Plans
- Appendix 20 - Estimated Development Cost plan
- Appendix 21 - Visual Impact Assessment
- Appendix 22 - Acoustic Report
- Appendix 23 - Landscape Plans
- Appendix 24 - Mitigation Measures
- Appendix 25 - Design Verification Statement
- Appendix 26 - Wind Report
- Appendix 27 - Geotechnical Assessment
- Appendix 28 - ADG Compliance Table
- Appendix 3 - Design report
- Appendix 4 - Approved DA plans DA 672 2023 JP
- Appendix 5 - DA consent 672 2023 JP
- Appendix 6 - Land and Environment Court judgement
- Appendix 7 - Connecting with Country Framework Report
- Appendix 8 - ESD Report
- Appendix 9 - BASIX and NatHERs
- Application_20250707224903
- DNU App 9 - BASIX Certificates
- Environmental Impact Statement - Dawes Ave Castle Hill
Response to Submissions4
Agency Advice7
Additional Information6
Recommendation2
Determination10
- Notice of Decision
- SSD-80229956 Assessment Report
- SSD-80229956 Development Consent
- SSD-80229956 Stamped Arch Plans Part 1 of 6
- SSD-80229956 Stamped Arch Plans Part 2 of 6
- SSD-80229956 Stamped Arch Plans Part 3 of 6
- SSD-80229956 Stamped Arch Plans Part 4 of 6
- SSD-80229956 Stamped Arch Plans Part 5 of 6
- SSD-80229956 Stamped Arch Plans Part 6 of 6
- SSD-80229956 Stamped Landscape Plans
Notifications1
What's near it
Where it is
- Suburb
- Castle Hill
- Council area
- The Hills Shire
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.