On the map
Part 3A project

Redfern Mixed Use Development (Gibbons St)

Decided: approved on 22 Oct 2010Mixed use

Where it is in the process

Approved on 22 Oct 2010

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination22 Oct 2010 (done)
  10. Approved22 Oct 2010

What it proposes

The portal gives no description.

Modifications

5 changes to the project after its decision, each assessed as a case of its own, newest first.

Redfern Mixed Use MOD 5 - Additional ParkingMP08_0112-Mod-5

Decided: approved on 18 Apr 2018 by the department (director)

/

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 4 - Strata Subdivision ChangesMP08_0112-Mod-4

Decided: approved on 4 Aug 2017 by the department (executive director)

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application5

See the 5 documents on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Construction & ParkingMP08_0112-Mod-3

Decided: approved on 6 Nov 2012 by the department (deputy director-general)

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Application6

See the 6 documents on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 2 - Loading & Unloading ConditionsMP08_0112-Mod-2

Decided: approved on 4 Nov 2011 by the department (deputy director-general)

Its 10 documents

Its page on the Planning Portal

Mod 1- Reduction Apartment & Basement LevelsMP08_0112-Mod-1

Decided: approved on 28 Feb 2011 by Dir(GLSP)

Its 29 documents

29 documents in 3 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

EA24

See the 24 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.