On the map
State significant development

Powerhouse Ultimo Revitalisation

Decided: approved on 24 Mar 2025Tourism and recreation

Where it is in the process

Approved on 24 Mar 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination24 Mar 2025 (done)
  9. Approved24 Mar 2025

What it proposes

The department's description

Revitalisation of the Powerhouse Ultimo museum, including:

- demolition of non-heritage elements of Ultimo Powerhouse building

- partial demolition of the Wran Building

- adaptive reuse of heritage items

- new museum spaces

- new public spaces

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

264 submissions: 244 from the public, 19 from organisations and 1 from public authorities

Object241
Support9
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Modification 2 - Extended Construction HoursSSD-67588459-Mod-2

Decided: approved on 9 Nov 2026 by the department (director) · 7 submissions

Extension of construction hours

Its 12 documents

12 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1
Modification Application3
Response to Submissions3
Additional Information1
Determination3
Consolidated Consent1

Its page on the Planning Portal

Powerhouse Ultimo Revitalisation MOD 1 - RebuildSSD-67588459-Mod-1

Decided: approved on 14 Nov 2025 by the department (executive director) · 32 submissions

Demolition and reconstruction the Wran Building and Galleria structure, changes to the Switch House including a new pitched roof and removal of the rooftop bar, internal changes across the development and removal of the loading dock.

Its 44 documents

44 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application10

See the 10 documents on the Planning Portal

Response to Submissions7

See the 7 documents on the Planning Portal

Agency Advice13

See the 13 documents on the Planning Portal

Additional Information7

See the 7 documents on the Planning Portal

Determination5

See the 5 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.