On the map
State significant development

Pitt Street North Over Station Development Stage 2

Decided: approved on 26 Feb 2021Mixed use

Where it is in the process

Approved on 26 Feb 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination26 Feb 2021 (done)
  9. Approved26 Feb 2021

What it proposes

The department's description

Design and construction of Pitt Street North Over Station Development

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

16 submissions: 3 from the public, 1 from organisations and 12 from public authorities

Object2
Support0
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

6 changes to the project after its decision, each assessed as a case of its own, newest first.

Pitt Street North OSD Stage 2 MOD 6 - Admin ChangeSSD-10375-Mod-6

Decided: approved on 3 Jul 2024 by the department (team leader)

Modification application seeking to modify Condition E30 to correct two minor errors/ misdescriptions

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Pitt Street North OSD Stage 2 MOD 4 - DesignSSD-10375-Mod-4

Decided: approved on 24 Nov 2023 by the department (director) · 2 submissions

Modification to proposed construction hours, removal of cranes, architectural plans and conditions.

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Pitt Street North OSD Stage 2 MOD 5 - Design & HFSSSD-10375-Mod-5

Decided: approved on 28 Jun 2023 by the department (team leader)

Modification seeks approval for the following: Modify the wording of Condition B11 for HFS obligations by extending timeframe Minor design to internal layout of male toilets on level 22-26

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Pitt Street North OSD Stage 2 MOD 3 - ElectrificalSSD-10375-Mod-3

Decided: approved on 24 Feb 2023 by the department (team leader)

Modification application to increase the height and form of the central roof element to accommodate additional plant to facilitate the electrification of the building and reinstate the terrace doors on Levels 10 and 11.

Its 14 documents

14 documents in 4 folders, each on the NSW Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Pitt Street North OSD Stage 2 MOD 2 - ConditionSSD-10375-Mod-2

Decided: approved on 26 Aug 2022 by the department (team leader)

Modification application to increase the height of the balustrade on the northern edge of the Level 10 terrace and refinement to wording of Condition B11 (Heritage Floor Space).

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Amendments1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Pitt Street North OSD Stage 2 MOD 1 - DesignSSD-10375-Mod-1

Decided: approved on 1 Jul 2022 by the department (team leader)

As a result of design development, a number of minor modifications and materiality clarifications are proposed to the PSN OSD SSD DA (SSD-10375). These changes are minor in nature and are anticipated to constitute a Section 4.55 (1A) modification.

Its 17 documents

17 documents in 4 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.