On the map
Part 4 development

Penrith Lakes DA 3

Decided: approved on 27 Jun 1995Mixed use

Where it is in the process

Approved on 27 Jun 1995

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination27 Jun 1995 (done)
  10. Approved27 Jun 1995

What it proposes

The portal gives no description.

Modifications

10 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 9 - Administrative ChangeDA3-Mod-9

Withdrawn: withdrawn

Its 3 documents

3 documents in 1 folder, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Administrative ChangeDA3-Mod-3

Decided: approved by Dir(MIA)

Its page on the Planning Portal

Mod 2 - Administrative ChangeDA3-Mod-2

Decided: approved by the Minister

Its page on the Planning Portal

Mod 1 - Administrative ChangeDA3-Mod-1

Decided: approved by the department (director)

Its page on the Planning Portal

DA3 Penrith Lakes Modification 10DA3-Mod-10

Decided: approved on 24 Apr 2026 by the department (executive director) · 10 submissions

This SSD modification application seeks to modify DA3 to increase the importation of 9.7 million tonnes of material across Lot 4 to increase the overall levels on average 1.32 metres on average across the site and up to 2.98 metres

Its 59 documents

59 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Response to Submissions16

See the 16 documents on the Planning Portal

Agency Advice18

See the 18 documents on the Planning Portal

Additional Information15

See the 15 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 8 - Administrative ChangeDA3-Mod-8

Decided: approved on 1 May 2020 by the department (director)

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 6 - Administrative ChangeDA3-Mod-6

Decided: approved on 8 Jan 2019 by Court

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 7 - Administrative ChangeDA3-Mod-7

Decided: approved on 28 Aug 2018 by the department (director)

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Agency Submissions3

See the 3 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 5 - Administrative ChangeDA3-Mod-5

Decided: approved on 6 Nov 2017 by the department (executive director) · 1 submission

Its 17 documents

Its page on the Planning Portal

Penrith Lakes Scheme MOD 4 - Import of fillDA3-Mod-4

Decided: approved on 30 Apr 2015 by the department (executive director) · 5 submissions

/

Its 9 documents

9 documents in 5 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Agency Submissions2

See the 2 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.