State significant development

Panorama Battery Energy Storage System

A 100 MW battery at 800 Mid-Western Highway, Evans Plains

Under way: at assessmentEnergy: batteriesDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW battery at 800 Mid-Western Highway, Evans Plains

The proponent proposes a battery energy storage system with a capacity of 100 MW and 200 MWh at 800 Mid Western Highway, Evans Plains, in the Bathurst Regional Council area. It would sit next to an existing 132 kV substation and connect to it by about 100 m of underground cable. The development footprint is 3.47 ha. The environmental impact statement (EIS) expects about 20 construction jobs and 1 operational job. No capital investment figure is stated.

The EIS is dated 31 May 2024. It drew 31 submissions: 24 objecting, 5 supporting and 2 commenting. The proponent has since amended the project twice, with the second amendment report dated February 2026, and has answered several requests for information. The case is at the stage where the department has asked for more information. After that, the department assesses it and recommends a decision.

Battery power capacity
100 MWEnvironmental Impact Statement
Battery storage capacity
200 MWhEnvironmental Impact Statement
Development footprint
3.47 haEnvironmental Impact Statement
Construction jobs
20 jobsEnvironmental Impact Statement
Operational jobs
1 jobsEnvironmental Impact Statement
Underground cable length
100 mEnvironmental Impact Statement

The department's description

A Battery Energy Storage System with a capacity of 100 MW / 200 MWh and associated ancillary infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

31 submissions: 26 from the public and 5 from organisations

Object24
Support5
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

122 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs5
EIS21
Response to Submissions9
Agency Advice43
Amendments24
Additional Information18

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.