On the map
Part 4 development

Orica Chlor-Alkali Plant

Decided: approved on 6 Nov 1998Industry and warehouses

Where it is in the process

Approved on 6 Nov 1998

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination6 Nov 1998 (done)
  10. Approved6 Nov 1998

What it proposes

The portal gives no description.

Modifications

7 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 2 - Chlor-Alkali Plant DemolitionDA35/98-Mod-2

Decided: approved by the department (executive director)

Its page on the Planning Portal

Mod 1 - Sodium HypochloriteDA35/98-Mod-1

Decided: approved by the department (executive director)

Its page on the Planning Portal

DA35/98-Mod-7 Gas-fired boilerDA35/98-Mod-7

Decided: approved on 28 Jul 2026 by the department (team leader)

Installation of new gas-fired boiler, roofed shelter, ancillary equipment, and extensions to existing pipework

Its 10 documents

10 documents in 4 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 6 Chlorine Liquefaction PlantDA35/98-Mod-6

Decided: approved on 21 Jul 2026 by the department (director) · 35 submissions

Construction and operation of a chlorine liquefaction plant in the Botany Industrial Park, with a maximum production capacity of 50 tonnes per day.

Its 50 documents

Its page on the Planning Portal

Orica Chlor-Alkali MOD 5 - Packaging FaciliyDA35/98-Mod-5

Decided: approved on 26 Oct 2018 by the department (director)

/

Its 16 documents

Its page on the Planning Portal

Mod 4 - Administrative ChangeDA35/98-Mod-4

Decided: approved on 10 Sep 2012 by the department (executive director)

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Submissions2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Administrative ChangeDA35/98-Mod-3

Decided: approved on 29 Sep 2009 by the department (executive director)

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

10 documents in 3 folders, each on the NSW Planning Portal

Determination6

See the 6 documents on the Planning Portal

Reports3

See the 3 documents on the Planning Portal

Other Documents1

See the document on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.