A 608 MW wind farm with battery near Armidale

Under way: at prepare eisEnergy: windRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 608 MW wind farm with battery near Armidale

The proponent proposes to build, operate and decommission the Northern Tablelands Wind Farm at 1188 Warrane Road, Boorolong, about 18 km north-west of Armidale. It lies in the Armidale Regional and Uralla Shire council areas. The wind farm would have a generating capacity of about 608 MW, with up to 76 turbines, and a battery of up to 800 MW and 1,000 MWh. The project area is about 7,671 ha. The preliminary development cost is stated only as more than $30 million.

The proponent lodged a scoping report dated 15 Sep 2025, and the Secretary's environmental assessment requirements (SEARs) have been issued. The proponent is now preparing an environmental impact statement (EIS). Next, the EIS is to be exhibited and the public can make submissions. No submissions have been made yet. The department then assesses the project and it is decided.

Wind farm generating capacity
608 MWScoping Report
Wind turbines
76 turbinesScoping Report
Battery power capacity
800 MWScoping Report
Battery storage capacity
1,000 MWhScoping Report
Project area
7,671 haScoping Report

The department's description

Construction, operation and decommissioning of a wind farm with up to 76 wind turbines, battery storage and associated infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.