North Shore Health Hub - Tower B Stage 2

Decided: approved on 10 Aug 2018Health

Where it is in the process

Approved on 10 Aug 2018

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination10 Aug 2018 (done)
  9. Approved10 Aug 2018

What it proposes

The portal gives no description.

Submissions

What the public, organisations and public authorities said, counted by where they stood.

5 submissions: 5 from organisations

Object0
Support0
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

NSHH Tower B Stg 2 MOD 2 - Roof form and materialSSD-8894-Mod-2

Decided: approved on 21 Jul 2020 by the department (director)

Change in plant room roof form from pitched metal to flat concrete.

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

NSHH Tower B Stage 2 MOD 1 - Design changesSSD-8894-Mod-1

Decided: approved on 25 Jul 2019 by the department (director)

Increase the height of building for Tower B from RL 138.35 to RL 139.3; minor amendment to the setbacks to Reserve Road, northern and western property boundaries; and reduce the gross floor area from 6,987 sqm to 6,876 sqm.

Its 11 documents

11 documents in 3 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.