Approved on 12 Aug 2024

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination12 Aug 2024 (done)
  9. Approved12 Aug 2024

What it proposes

The department's description

Construction and operation of a new hospital development including landscaping, internal roads and access, at-grade and multi-deck car parking, utility/service connections and supporting infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

18 submissions: 12 from the public, 4 from organisations and 2 from public authorities

Object5
Support3
Comment10

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Shellharbour Hospital Mod-3 - Shared pathway conditionsSSD-57064458-Mod-3

Decided: approved on 7 Oct 2026 by the department (executive director)

Modification of condition wording relating to delivery of the shared pathway.

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Shellharbour Hospital MOD 2 - Helipad and designSSD-57064458-Mod-2

Decided: approved on 5 Feb 2026 by the department (director) · 3 submissions

Amendments including addition of a rooftop helipad and design changes to car parking layout, building facades and landscaping.

Its 23 documents

23 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application12

See the 12 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Shellharbour Hospital MOD 1 - Design changesSSD-57064458-Mod-1

Decided: approved on 4 Jul 2025 by the department (team leader)

Amendments including changes to carparking layout, internal and external alterations, changes to landscaping and planting schedule, external materials and finishes and minor increase in building height of the hospital and multideck carpark.

Its 19 documents

19 documents in 3 folders, each on the NSW Planning Portal

Modification Application14

See the 14 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.