Decided: approved on 30 Sep 2004Quarries

Where it is in the process

Approved on 30 Sep 2004

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination30 Sep 2004 (done)
  10. Approved30 Sep 2004

What it proposes

The portal gives no description.

Modifications

13 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 6 - Increased Extraction AreaDA470-11-2003-Mod-6

Decided: approved by the Independent Planning Commission · 11 submissions

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 5 - Extension to Extraction AreaDA470-11-2003-Mod-5

Decided: approved by the department (director)

Its 5 documents

5 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 4 - Administrative ChangeDA470-11-2003-Mod-4

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 3 - Administrative ChangeDA470-11-2003-Mod-3

Decided: approved by the department (executive director)

Its page on the Planning Portal

Mod 2 - Vegetation Offsets and Transport RouteDA470-11-2003-Mod-2

Decided: decided by the department (director)

Its 3 documents

3 documents in 1 folder, each on the NSW Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - New Amenities BlockDA470-11-2003-Mod-1

Decided: approved by the department (executive director)

Its 2 documents

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Modification 13 Dunmore Quarry Pit ExtensionDA470-11-2003-Mod-13

Decided: approved on 26 Jun 2024 by the department (director) · 5 submissions

Extension of the quarry pit to the north, increase in extraction depth and extend quarry life to 2043.

Its 30 documents

30 documents in 6 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice19

See the 19 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Dunmore Quarry MOD 12 - Dispatch LimitsDA470-11-2003-Mod-12

Decided: approved on 10 Sep 2021 by the department (director)

Deletion of consent condition Schedule 3 condition 7A (a-c) which imposes limits on hourly laden truck dispatches

Its 19 documents

19 documents in 7 folders, each on the NSW Planning Portal

Preparation of Modification Report3

See the 3 documents on the Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Recommendation3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 11 - Increased Transport TonnageDA470-11-2003-Mod-11

Decided: approved on 15 Mar 2019 by the department (director)

Its 18 documents

Its page on the Planning Portal

Mod 9 - Extension to extraction areaDA470-11-2003-Mod-9

Decided: approved on 22 Sep 2017 by the department (director)

Its 16 documents

Its page on the Planning Portal

Mod 10 - Dam capacityDA470-11-2003-Mod-10

Decided: approved on 22 Jun 2017 by the department (director)

Its 9 documents

Its page on the Planning Portal

Mod 8 - Administrative ChangeDA470-11-2003-Mod-8

Decided: approved on 17 Nov 2016 by the department (director)

Its 10 documents

Its page on the Planning Portal

Mod 7 - Proposed Blending PlantDA470-11-2003-Mod-7

Decided: approved on 20 Oct 2015 by the department (director)

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

EA1

See the document on the Planning Portal

Submissions2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

49 documents in 7 folders, each on the NSW Planning Portal

Management Plans and Strategies19

See the 19 documents on the Planning Portal

Agreements1

See the document on the Planning Portal

Community Consultative Committees and Panels2

See the 2 documents on the Planning Portal

Reports13

See the 13 documents on the Planning Portal

Independent Reviews and Audits7

See the 7 documents on the Planning Portal

Notifications1

See the document on the Planning Portal

Other Documents6

See the 6 documents on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.