On the map
State significant development

Narrabri South Solar Farm

Decided: approved on 21 Dec 2018Energy: solarNeighbourhood scale

Where it is in the process

Approved on 21 Dec 2018

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination21 Dec 2018 (done)
  8. Approved21 Dec 2018

What it proposes

The department's description

Development of a 60 megawatt solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

6 submissions: 2 from the public and 4 from organisations

Object1
Support1
Comment4

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

MOD 1 Powerline re-alignment and Battery SystemSSD-8387-Mod-1

Under way: at prepare mod report

Realignment of grid connection route and incorporation of a battery energy storage system

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.