Mixed-use development, 307-315 Parramatta Road
A 12-storey mixed-use building at 307-315 Parramatta Road
Where it is in the process
Approved on 7 Sep 2026
What it proposes
AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 12-storey mixed-use building at 307-315 Parramatta Road
The project is a 12-storey mixed-use building at 307-315 Parramatta Road, Leichhardt, in the Inner West Council area. It has shop top housing for 120 units, with 4% of residential floor area for affordable housing, and 3 ground floor retail premises. The site is 2,686.4 m² and the building would reach 48.6 m. The estimated development cost is $68,505,673. The consent sets 148 car parking spaces. It includes public domain works and remediation of contaminated land.
The environmental impact statement (EIS) was exhibited from 3 December 2025 to January 2026 and drew 24 submissions: 14 objecting, 7 supporting and 3 commenting. The proponent lodged a submissions report on 3 July. The department's assessment found the project acceptable. As the Minister's delegate, the Director of Housing Delivery Assessments approved it on 7 Sep 2026, with conditions. Next, the proponent must meet the conditions before construction.
- Estimated development cost
- $68.5MAssessment Report
- Residential units
- 120 dwellingsInstrument of Consent
- Maximum building height
- 48.6 mAssessment Report
- Site area
- 2,686.4 m²Assessment Report
- Car parking spaces
- 148 car spacesInstrument of Consent
- Building storeys
- 12 storeysInstrument of Consent
The department's description
Construction of a 12-storey mixed-use development consisting of 120 residential units, 8 affordable living units, 3 ground floor retail premises, public domain works, embellishment, site landscaping and remediation of contaminated land
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
24 submissions: 22 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
141 documents in 9 folders, each on the NSW Planning Portal
Early Consultation1
Notice of Exhibition1
SEARs5
EIS57
- Appendix 10 Civil and Stormwater Plans
- Appendix 11A Integrated Water Management Report
- Appendix 11B Flood Impact and Risk Assessment
- Appendix 12A Transport Impact Assessment
- Appendix 12B Preliminary CTPMP
- Appendix 13 Pedestrian Wind Assessment
- Appendix 14 Solar Reflectivition Analysis
- Appendix 15 Noise and Vibration Impact Assessment
- Appendix 16 Acid Sulfate Soils Review
- Appendix 17A Detailed Site Investigation
- Appendix 17B Remediation Action Plan
- Appendix 18 Salinity Assessment
- Appendix 19A Hydrogeological Report Including DMP and GSA
- Appendix 19B Ground Water Seepage Analysis
- Appendix 19C Groundwater Level Monitoring Report
- Appendix 1A Key Legislation
- Appendix 1B Relevant SEPPs
- Appendix 1C Compliance table Inner West LEP 2022
- Appendix 1E Engagement Outcomes Tables
- Appendix 1F Mitigation Measures table
- Appendix 1G PRCUTS Implementation
- Appendix 2 SEARS Table
- Appendix 20 Geotechnical Investigation
- Appendix 21 Fire Engineering Report
- Appendix 22 Accessibility Report
- Appendix 23 Regulatory Compliance Report
- Appendix 24 Statement of Heritage Impact
- Appendix 25 Historical Archaeological Assessment
- Appendix 26 Aborigional Cultural Herit Due Diligence Advice
- Appendix 27 Connecting With Country Report
- Appendix 28 BDAR Waiver
- Appendix 29 OWMP
- Appendix 2A Additional SEARS Requirements
- Appendix 2B Inner West Requirements
- Appendix 3 Affordable Housing Nomination Letter
- Appendix 30 Social Impact Assessment
- Appendix 31 Stakeholder Engagement Report
- Appendix 32 ESD Report
- Appendix 33 BASIX Certificate
- Appendix 33A NatHERs Certificates
- Appendix 33B Stamped Plans
- Appendix 33C Thermal Performance Specification
- Appendix 34 CPTED Report
- Appendix 35 Legal Advice Letter
- Appendix 36 Visual Impact Assessment
- Appendix 37 Arboricultural Impact Assessment
- Appendix 38 Photomontage
- Appendix 39 Cl.4.6 - Unit Mix
- Appendix 4 Estimated Development Cost Report
- Appendix 5 Architectural Drawings
- Appendix 6 Design Verification Statement
- Appendix 7 Urban Design Report
- Appendix 8 Survey Plan
- Appendix 9A Landscape Plan
- Appendix 9B Landscape Report
- Appendix 1D ADG compliance table
- Environmental Impact Statement
Response to Submissions2
Agency Advice12
- Response #1 - Air Services Australia
- Response #1 - Ausgrid
- Response #1 - CASA
- Response #1 - CPHR
- Response #1 - Inner West Council - Holding Submission
- Response #1 - Inner West Council Objection
- Response #1 - Inner West Council Objection - Attachment A
- Response #1 - Inner West Council Objection - Attachment B
- Response #1 - NSW DCCEEW Water Group
- Response #1 - NSW SES
- Response #1 - Sydney Water
- Response #1 - TfNSW
Additional Information55
- Appendix 1 - Architecutral Plans
- Appendix 1 - Register of Submissions
- Appendix 10 - Architectural Plans
- Appendix 11 - Photomontage
- Appendix 12 - Design Verification Statement
- Appendix 13 - Urban Design Report
- Appendix 14 - Landscape plan
- Appendix 15 - Landscape Report
- Appendix 16 - Visual Impact Assessment
- Appendix 17 - Herritage Impact Assessment Letter
- Appendix 18 - Affordable Housing Provide Letter
- Appendix 19 - Access Report
- Appendix 2 - Flood Impact and Risk Assessment Letter
- Appendix 2 - Key Legislation
- Appendix 20 - Regulatory Compliance Report
- Appendix 21 - Fire Engineering Letter
- Appendix 22 - BASIX Certificate
- Appendix 22A - Stamped Plans
- Appendix 22B - NatHERS Certificate
- Appendix 23 - ESD Report
- Appendix 24 - Embodied Emission
- Appendix 25 - Thermal Specification
- Appendix 26 - Solar Reflectity Assessment
- Appendix 27 - Pedestrian Wind Assessment
- Appendix 28 - Accoustic Letter
- Appendix 29 - Transport Impact Assessment
- Appendix 3 - Relevant SEPPs
- Appendix 3 - Typical Floor to Ceiling Section
- Appendix 30 - Construction Traffic Management Plan
- Appendix 31 - Civil Plans
- Appendix 32 - Integrated Water Management Report
- Appendix 32A - Drains Model
- Appendix 32B - MUSIC Model
- Appendix 33- Flood Impact Risk Assessment
- Appendix 34 - Hydrogeological Report including DMP and GSA
- Appendix 35 - Operational Waste Managment Plan
- Appendix 36 - Groundwater Seepage Analysis
- Appendix 37 - Salinity Review Letter
- Appendix 38 - Acid Sulfate Risk Letter
- Appendix 39 - Detailed Site Investigation
- Appendix 4 - Compliance Table Inner West LEP 2022
- Appendix 4 - Services Engineering Statement
- Appendix 40 - Remedial Action Plan
- Appendix 41 - Stratum Plan
- Appendix 5 - Cl.4.6 - Unit Mix
- Appendix 5 - Connecting with Country Letter
- Appendix 6 - CPTED Report
- Appendix 6 - Noise and Vibration Impact Assessment Letter
- Appendix 7 - Mitigation Measures table
- Appendix 8 - Estimated Development Cost and Employment
- Appendix 9 - Social Impact Assessment
- Letter - Request for Additional Information
- Response to RFI Dated 13 August 2026
- SSD-83721209 - Request for Additional Information #2
- Submissions + Amendment Report
What's near it
Where it is
- Suburb
- Leichhardt
- Council area
- Inner West
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.