On the map
State significant development

Matraville Paper Mill

Decided: approved on 20 Jul 2007Industry and warehouses

Where it is in the process

Approved on 20 Jul 2007

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination20 Jul 2007 (done)
  8. Approved20 Jul 2007

What it proposes

The department's description

Orora Paper Mill

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Opal Paper Mill MOD 10 - Waste HandlingMP05_0120-Mod-10

Decided: approved on 22 Dec 2021 by the department (director)

Modification to: - construct and operate a rejects handling facility on site to minimise waste generation associate with the paper mill operations - extend the finished product store to support the ongoing operation and operational efficiency.

Its 28 documents

28 documents in 5 folders, each on the NSW Planning Portal

Modification Application14

See the 14 documents on the Planning Portal

Agency Advice7

See the 7 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Opal Paper Mill MOD 9 - Increased Production LimitMP05_0120-Mod-9

Decided: approved on 1 Aug 2019 by the department (director)

An increase in the limit of production from 425,000 tonnes of paper per annum to 500,000 tonnes of paper per annum;

Its 14 documents

14 documents in 5 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Preparation of Modification Report3

See the 3 documents on the Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Additional Information6

See the 6 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Opal Paper Mill MOD 8 - DemolitionMP05_0120-Mod-8

Decided: approved on 29 Oct 2018 by the department (director) · 8 submissions

/

Its 13 documents

13 documents in 4 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

SEE9

See the 9 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.