On the map
State significant development

Interlink Distribution Centre

A 44,654 m² warehouse at Sarah Andrews Close, Erskine Park

Under way: at exhibitionIndustry and warehousesNeighbourhood scale

Where it is in the process

At exhibition, since 27 Oct 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition27 Oct 2026 (current stage)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

Open for comment until 24 Nov 2026. Anyone can make a submission on its page on the Planning Portal.

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 44,654 m² warehouse at Sarah Andrews Close, Erskine Park

The proponent proposes to demolish the existing warehouse buildings at 35-44 Sarah Andrews Close, Erskine Park, in the Penrith council area, and build one warehouse and distribution centre with ancillary offices. It would have a gross lettable area of 44,654 m², be up to 16.8 m high excluding rooftop plant and solar, and have 176 car parking spaces. It would operate 24 hours a day, 7 days a week, on a site of 86,590 m². The environmental impact statement (EIS) gives a capital investment of $73,004,901, 124 construction jobs and 248 operational jobs.

The EIS was exhibited from 27 Oct 2026 to 24 Nov 2026, and no submissions have been recorded so far. The Secretary's environmental assessment requirements were issued on 22 Apr 2026. Next, the proponent responds to submissions, and the department assesses the project and makes a recommendation before a decision is made.

Capital investment
$73MEnvironmental Impact Statement
Gross lettable area
44,654 m²Environmental Impact Statement
Maximum building height
16.8 mEnvironmental Impact Statement
Car parking spaces
176 car spacesEnvironmental Impact Statement
Construction jobs
124 jobsEnvironmental Impact Statement
Operational jobs
248 jobsEnvironmental Impact Statement
Site area
86,590 m²Environmental Impact Statement

The department's description

Approval is sought for the construction and 24‑hour operation of a single warehouse and distribution centre. The development includes an ancillary office, associated car parking, landscaping and hardstand areas.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.