On the map
State significant development

Huntlee New Town - Stage 2

Huntlee New Town Stage 2 masterplan and Village 2 subdivision

Under way: at assessmentMixed useRegional scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its SSD-70748466 Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Huntlee New Town Stage 2 masterplan and Village 2 subdivision

The proponent proposes a concept masterplan for Stage 2 of Huntlee New Town at North Rothbury, across the Singleton Shire and Cessnock City council areas. It covers the rest of the town centre, Villages 2, 3 and 4, and a large lot residential area south of the site on Old North Road. It also seeks detailed approval for the subdivision of the Village 2 residential area. No capital investment, number of homes or lots is stated.

The environmental impact statement (EIS), dated 28 Jun 2024, was exhibited and drew 39 submissions: 33 objecting, 1 supporting and 5 commenting. The proponent has responded to submissions and sent further information and amended plans. The department is now assessing the project with advice from other agencies. Next, it writes an assessment report and the project is determined.

Public submissions
39 submissionsPortal page
Submissions objecting
33 submissionsPortal page

The department's description

A Concept Master plan for Stage 2 site including the residue of Town Centre, Villages 2, 3 and 4 and a large lot residential area located to the south of the site on Old North Road.

Detailed subdivision application for Village 2 residential area

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

39 submissions: 34 from the public, 3 from organisations and 2 from public authorities

Object33
Support1
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

169 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs2
SEARs2
EIS54
Response to Submissions31
Agency Advice29
Additional Information50

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.