Huntlee New Town - Stage 2
Huntlee New Town Stage 2 masterplan and Village 2 subdivision
Where it is in the process
At assessment
What it proposes
AI summary. Written from this project's page and its SSD-70748466 Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Huntlee New Town Stage 2 masterplan and Village 2 subdivision
The proponent proposes a concept masterplan for Stage 2 of Huntlee New Town at North Rothbury, across the Singleton Shire and Cessnock City council areas. It covers the rest of the town centre, Villages 2, 3 and 4, and a large lot residential area south of the site on Old North Road. It also seeks detailed approval for the subdivision of the Village 2 residential area. No capital investment, number of homes or lots is stated.
The environmental impact statement (EIS), dated 28 Jun 2024, was exhibited and drew 39 submissions: 33 objecting, 1 supporting and 5 commenting. The proponent has responded to submissions and sent further information and amended plans. The department is now assessing the project with advice from other agencies. Next, it writes an assessment report and the project is determined.
- Public submissions
- 39 submissionsPortal page
- Submissions objecting
- 33 submissionsPortal page
The department's description
A Concept Master plan for Stage 2 site including the residue of Town Centre, Villages 2, 3 and 4 and a large lot residential area located to the south of the site on Old North Road.
Detailed subdivision application for Village 2 residential area
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
39 submissions: 34 from the public, 3 from organisations and 2 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
169 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs2
EIS54
- AA - Operational Waste Management Plan
- Appendix A - SEARs Compliance Table
- Appendix B - Statutory Compliance Table
- Appendix C - Community Engagement Table
- Appendix D - Mitigation Measures
- Appendix II - DCP Compliance Table
- BB - Construction Waste Management Plan
- CC - Public Benefit Offer - State
- DD - Public Benefit Offer - Singleton
- E - Site Survey
- EE - Issued SEARs
- F1 - Subdivision Plans Village 2 Detailed
- F2 - Village 2 Indicative Staging
- F3 - Concept Subdivision Plan
- F4 - Subdivision Plans Village 2 Lot Type
- F5 - Subdivision Plans Village 2 North Concept Lot Type
- F6 - Subdivision Plans Village 3 Concept Lot Type
- F7 - Subdivision Plans Old North Road Concept Lot Type
- FF - ESD Report
- G - Urban Design Strategy_HR
- G - Urban Design Strategy_LR
- GG - Engagement Outcomes Report
- H - Draft Huntlee DCP
- HH - Green Travel Plan
- I - Landscape Plans_HR
- I - Landscape Plans_LR
- J1 - Village 2 Central and South Detailed Area
- J2 - Indicative Village 3 Concept Area
- J3 - Indicative Town Centre North Concept Area
- J4 - Indicative Village 2 North Concept Area
- J5 - Indicative Old North Road Concept Area
- J6 - Concept Stormwater Plans
- J7 - Intersection Concept Designs
- JJ - Comparison Version of Huntlee DCP
- K - Flood Impact Assessment
- KK - SSDA Declaration
- L - Physical Infrastructure Report
- LL - Biodiversity Exemption Certificate
- M - Traffic Impact Assessment
- N - Ecological Report
- O - Bushfire Assessment
- P - ACHAR (Public)
- Q - Historic Heritage Assessment
- R - Geotechnical Report
- S - Mine Subsidence Report
- SSD-70748466 Environmental Impact Statement
- SSD-70748466 Summary Report
- T - Preliminary Site Investigation
- U - Community Infrastructure Needs Analysis
- V - Social Impact Assessment
- W - Economic Benefits Statement
- X - Operational Noise and Vibration Impact Assessment
- Y - Construction Noise and Vibration Impact Assessment
- Z - Preliminary CMP
Response to Submissions31
- AA_Updated Community Infrastructure Needs Analysis
- A_Submissions Register
- BB_Updated Social Impact Assessment Report
- B_Updated Mitigation Measures
- CC_Updated Economic Benefits Statement
- C_Updated Subdivision Plans Village 2 Detailed
- DD_Updated Construction Noise & Vibration Impact Assessment
- D_Updated Village 2 Indicative Staging
- E_Updated Concept Subdivision Plan
- F_Updated Subdivision Plans Village 2 Lot Type
- G_Updated Subdivision Plans Village 3 Concept Lot
- H_ Updated Subdivision Plans Yield Plan
- I_Updated Urban Design Strategy
- J_Updated Draft Huntlee DCP
- K - Updated DCP Compliance and Amendments Table
- L_Updated Landscape Plan (High Res)
- L_Updated Landscape Plan (Low Res)
- M_Updated Village 2 Central & South Detailed Area Eng Plans
- N_Updated Village 3 Concept Area Engineering Plans
- O_Updated Indicative Old North Road Concept Area Eng Plans
- P_Updated Intersection Concept Designs
- Q_Updated Physical Infrastructure Report
- Request RTS Letter5720732
- Response to Submissions Report
- S_TfNSW Intersection Design RTS Response
- U_Updated Historic Heritage Assessment Report
- V_Updated Preliminary Site Investigation
- W_Review of Overview Remedial Action Plan
- X_Updated Preliminary Geotechnical Assessment
- Y_Bushfire Response to Rural Fire Services Statement
- Z_Biodiversity Response to Submissions Statement
Agency Advice29
- 1900130494 Ausgrid Response
- BCS - Huntlee New Town Stage 2 - Flooding
- BCS response re Huntlee New Town Stage 2 EIS
- CPHR Response - Huntlee New Town - Stage 2 – RTS
- Cessnock City Council - RtS submission Huntlee New Town SSD-70748466
- Cessnock City Council Submission -Huntlee Stage 2 EIS
- Cessnock City Council URA plan
- DCCEEW Water advice - Huntlee New Town Stage 2 - EIS
- Department of Education - Huntlee Stage 2 Advice
- Department of Education - RtS advice
- DoE Submission - Huntlee New Town - Stage 2
- EPA - OUT - Response letter - Huntlee New Town Stage 2
- HNSW ACH - EIS - Huntlee New Town - Stage 2 - SSD-70748466
- HNSW ACH - Other - Huntlee New Town Stage 2 - SSD-70748466
- Heritage NSW - (Heritage Council) - RtS advice
- Heritage NSW ACH - RtS advice - Huntlee New Town - Stage 2 - SSD-70748466
- HeritageNSW_EH_EIS_SSD-70748466_HMS-6788
- Hunter Water - RtS advice - Huntlee New Town Stage 2
- Hunter Water - SSD-70748466
- Huntlee New Town - Stage 2 RTS RFS Response
- NSW DCCEEW Water Group RtS advice
- NSW Health - Huntlee Stage 2-signed
- RFS - Huntlee New Town - SSD-70748466
- RFS advice on additional information - March 2026
- RFS advice on additional information of Nov 2025
- Subsidence Advisory - Huntlee Stage 2 EIS - EOTH24-00219
- TfNSW - RtS advice
- TfNSW Response
- TfNSW advice on additional information Nov 2025
Additional Information50
- 2210308_RFI Letter and Response Table_RevA1
- ACHAR Addendum - Aug 2026
- Additional traffic - A11 and A1 Threshold Review
- Amendment Report - Final RFI_FINAL
- Amendment letter
- Appen J - Village 2 & South engineering
- Appendix A_Updated Concept Subdivision Plan
- Appendix B - Updated Landscape Report
- Appendix B_Updated Village 2 Indicative Staging Plan
- Appendix C - Updated Concept Subdivision Plan
- Appendix C_Concept Subdivision Plan Proposed Changes
- Appendix D - Updated Subdivision Plan Village 2
- Appendix D_Updated Subdivision Plans Village 2 Lot Type
- Appendix E - Updated BAL plan
- Appendix E_Updated Yield Plan
- Appendix F - Updated Village 2 Lot Type Plan
- Appendix F_Land Dedication Plan
- Appendix G - Village 2 Indicative Staging Plan
- Appendix G_Updated Urban Design Stategy and Report
- Appendix H - Updated Subdivision Plans Yield Plan
- Appendix H_Updated Draft Huntlee Development Control Plan
- Appendix I - Updated Concept Subdivision – Changes
- Appendix I_Updated Landscaping and Open Space PlanHR
- Appendix I_Updated Landscaping and Open Space PlanLR
- Appendix K_Indicative Village 3 Concept Area
- Appendix L_Updated Physical Infrastructure Report
- Appendix M_Updated Ecological Report
- Appendix N_Updated Aboriginal Cultural Heritage Assessment
- Appendix O_Updated Historical Heritage Assessment
- Appendix P_Updated Economic Benefits Statement
- Appendix Q_Updated Operational Noise and Vibration
- Appendix R_Updated Construction Noise and Vibration
- Appendix S_Updated Green Travel Plan
- Appendix T_Updated Community Infrastructure Needs Analysis
- Appendix U_Updated Social Impact Assessment
- Appendix V_Updated Detailed Subdivision Plans For Village 2
- Appendix W_Updated Subdivision Plans Village 3 Concept Lot
- Appendix X_Works Area Plan
- Appendix Y_Updated Bushfire Assessment Report
- Attachment A - MJD RFS Response
- Attachment B - Bentham House Heritage
- Civil Plans – Village 2 Central and -Part3
- Civil Plans – Village 2 Central and South - Part1
- Civil Plans – Village 2 Central and South- Part2
- Civil Plans – Village 2 Central and South-Part4
- Civil Plans – Village 2 Central and South-Part5
- Huntlee Stage 2 RFI 1 Letter
- Request for Additional Information
- Request for Additional Information - November Signed
- Traffic sensitivity Modelling
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.