On the map
State significant development

Howlong Sand and Gravel Quarry Expansion

Decided: approved on 16 Dec 2022Quarries

Where it is in the process

Approved on 16 Dec 2022

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination16 Dec 2022 (done)
  9. Approved16 Dec 2022

What it proposes

The department's description

Expansion of an existing sand and gravel quarry from 30,000 tonnes p.a. to 330,000 tonnes p.a.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

57 submissions: 40 from the public, 4 from organisations and 13 from public authorities

Object27
Support10
Comment20

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Howlong Quarry Modification 1SSD-8804-Mod-1

Under way: at prepare mod report

The modification seeks to include fuel storage with the Quarry Site and the consolidation and reconfiguration of cadastral boundaries within the property through a subdivision.

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.