Hampton Park Solar Farm
A 180 MW solar farm and 800 MWh battery near Dubbo
Where it is in the process
At exhibition, since 19 Nov 2026
Open for comment until 17 Dec 2026. Anyone can make a submission on its page on the Planning Portal.
What it proposes
AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Out of date. This summary was written when the project was at Prepare EIS (summarised 19 Nov 2026); it has since moved to Exhibition.
A 180 MW solar farm and 800 MWh battery near Dubbo
The proposal is a solar farm of 180 MW with a battery energy storage system of 800 MWh and associated infrastructure, at 77R Wellington Road, Dubbo, in the Dubbo Regional Council area. No capital investment, site area or job numbers are stated.
The case is at the stage of preparing the environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) have been issued. An EIS dated November 2026 and its appendices are listed among the documents, and an exhibition notice is listed, but no exhibition dates are given. No submissions have been received yet. Next, the EIS is exhibited and the public can make submissions. The proponent then responds to them and the department assesses the project and makes a recommendation before it is decided.
- Solar farm capacity
- 180 MWPortal page
- Battery storage capacity
- 800 MWhPortal page
The department's description
Development of a 180 megawatt solar farm with an 800 megawatt hour battery energy storage system and associated infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
43 documents in 6 folders, each on the NSW Planning Portal
Notice of Exhibition1
Early Consultation6
Request for SEARs2
SEARs1
EIS21
- Appendix D - Community Consultation Evidence
- Appendix E - Community Engagement Summary Report
- Appendix F.1 - BDAR
- Appendix F.10 - Preliminary Site Investigation
- Appendix F.11.1 - Flood Impact Risk Assessment
- Appendix F.11.2 - Stormwater Strategy Report
- Appendix F.11.3 - Concept Stormwater Plan
- Appendix F.11.4 - Site Water Balance
- Appendix F.12 - Social Impact Assessment
- Appendix F.2 - ACHAR
- Appendix F.3.1 - LCVIA
- Appendix F.3.2 - Glint and Glare Assessment
- Appendix F.4 - Noise and Vibration Assessment
- Appendix F.5 - Preliminary Hazards Assessment
- Appendix F.6 - Bushfire Assessment Report
- Appendix F.7 - Agricultural Impact Assessment
- Appendix F.8 - Traffic Impact Assessment
- Appendix F.9.1 - Soil Survey and LSC
- Appendix F.9.2 - Erosion and Sediment Control Plan
- Application Form
- Environmental Impact Statement
Agency Advice12
- Crown Lands SEARs Advice
- DCCEEW CPHR SEARs Advice
- DCCEEW Water Group SEARs Advice
- DPIRD Agriculture SEARs Advice
- Dubbo Regional Council SEARs Advice
- FRNSW SEARs Advice
- HNSW ACH SEARs Advice
- HNSW EH SEARs Advice
- Mid-Western Regional Council SEARs Advice
- NSW Resources SEARs Advice
- RFS SEARs Advice
- TfNSW SEARS Advice
What's near it
Where it is
- Suburb
- Dubbo
- Council area
- Dubbo Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.