On the map
State significant development

Boree Solar Farm

A 250 MW solar farm and battery near Geurie

Under way: at prepare eisEnergy: solarRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 250 MW solar farm and battery near Geurie

The proponent proposes a solar farm with a capacity of up to 250 MW (direct current) and 200 MW (alternating current), plus a battery that can deliver 200 MW for four hours, or 800 MWh. It would sit on a site of about 1,322 ha, with a development footprint of about 981 ha, north of Geurie in the Dubbo Regional Council area. It would have up to 600,000 solar panels and connect into the existing 132 kV Essential Energy network on the site. No capital investment or job numbers are stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). A scoping report was lodged and the Secretary's environmental assessment requirements (SEARs) have been issued, with advice from agencies. No submissions have been made yet. Next, the proponent submits the EIS, which is then exhibited so the public can make submissions. The department then assesses it.

Solar capacity (DC)
250 MWScoping Report
Battery power capacity
200 MWScoping Report
Battery storage capacity
800 MWhScoping Report
Project site area
1,322 haScoping Report
Development footprint
981 haScoping Report
Solar panels
600,000 modulesScoping Report

The department's description

Development of a 250 megawatt solar farm with 200 megawatt / 800 megawatt hour battery energy storage system and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.