Gundary Solar Farm
A 320 MW solar farm and battery at Gundary, near Goulburn
Where it is in the process
At assessment
What it proposes
AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 320 MW solar farm and battery at Gundary, near Goulburn
The proponent proposes a solar farm with energy storage at 961 Windellama Road, Gundary, about 10 km south-east of Goulburn in the Goulburn Mulwaree area. The portal describes it as 320 MW. The environmental impact statement (EIS) describes about 400 MWp of solar panels and a battery of up to 555 MWp / 1,570 MWh, on a 702 ha project area. It gives a capital investment of about $650 million and 155 direct construction jobs.
The EIS is dated October 2024. It drew 169 submissions: 152 objecting, 16 supporting and 1 commenting. The proponent responded to submissions and lodged an amendment report. The department asked for more information several times, and the case is at the "More Information Required" stage. Next, the department assesses the project, then prepares its assessment report and the project is determined. No decision has been made.
- Capital investment
- $650MEnvironmental Impact Statement
- Solar capacity (portal description)
- 320 MWPortal page
- Battery storage capacity
- 1,570 MWhEnvironmental Impact Statement
- Project area
- 702 haEnvironmental Impact Statement
- Development footprint
- 512 haEnvironmental Impact Statement
- Direct construction jobs
- 155 jobsEnvironmental Impact Statement
- Total jobs during operations
- 14 jobsEnvironmental Impact Statement
- Public submissions
- 169 submissionsPortal page
The department's description
Development of a 320 MW solar farm with energy storage and associated infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
169 submissions: 153 from the public, 15 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
85 documents in 8 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
SEARs14
- Issued SEARs
- SEARS Advice - Transgrid
- SEARs Advice - Biodiversity Conservation Division
- SEARs Advice - DPE Water
- SEARs Advice - DPI Agriculture
- SEARs Advice - DPI Fisheries
- SEARs Advice - Fire & Rescue NSW
- SEARs Advice - Goulburn Mulwaree Council
- SEARs Advice - Heritage NSW ACH
- SEARs Advice - MEG-GSNSW
- SEARs Advice - NSW RFS
- SEARs Advice - Resource Regulator
- SEARs Advice - Transport for NSW
- SEARs Advice - WaterNSW
EIS24
- Appendix 1 SEARS
- Appendix 10 Soil and Agricultural Impact Assessment
- Appendix 11 Landscape and Visual Impact Assessment
- Appendix 12 Glint and Glare Assessment
- Appendix 13 Noise and Vibration Impact Assessment
- Appendix 14 Traffic Impact Assessment
- Appendix 15 Water Resources Impact Assessment
- Appendix 16 Preliminary Hazard Analysis
- Appendix 17 Bushfire Assessment
- Appendix 18 Social Impact Assessment
- Appendix 19 Economic Impact Assessment
- Appendix 2 Consolidated Mitigation Measures
- Appendix 20 Waste Management Plan
- Appendix 21 Cumulative Impact Scoping Summary
- Appendix 22 EIS Summary
- Appendix 3 List of Receivers
- Appendix 4 Detailed Maps and Plans
- Appendix 5 Statutory Compliance Table
- Appendix 6 Record of Stakeholder Engagement
- Appendix 7 BDAR
- Appendix 8 Aboriginal Cultural Heritage Assessment
- Appendix 9 Historical Heritage Impact Assessment
- Application
- Environmental Impact Statement
Response to Submissions9
Agency Advice27
- CPHR RTS Advice
- Crown Lands RTS Advice
- DPIRD Agriculture RTS Advice
- DPIRD Fisheries RTS Advice
- EIS - GMC Holding Submission
- EIS Advice - BCS
- EIS Advice - Crown Lands
- EIS Advice - DPI Agriculture
- EIS Advice - FRNSW
- EIS Advice - Fisheries
- EIS Advice - HNSW ACH
- EIS Advice - Heritage NSW
- EIS Advice - NSW DCCEEW Water
- EIS Advice - NSW RFS
- EIS Advice - NSW Resources
- EIS Advice - TfNSW
- EIS Advice - WaterNSW
- FRNSW RTS Advice
- GMC RTS Advice
- HNSW ACH RTS Advice
- HNSW EH RTS Advice
- NSW DCCEEW Water RTS Advice
- NSW RFS RTS Advice
- NSW SES RTS Advice
- NSWR RTS Advice
- TfNSW RTS Advice
- WaterNSW RTS Advice
Amendments2
Additional Information7
- Gundary RFI Response - 19 Oct 2026
- Gundary Solar Farm - RFI response Feb 25
- Gundary Updated TIA - Oct 2026 - Annexure C
- RFI Response - Preliminary Site Investigation
- Request for Additional Information 26 September 2025
- Request for Additional Information 4 September 2025
- Request for Additional Information July 2025
What's near it
Where it is
- Suburb
- Gundary
- Council area
- Goulburn Mulwaree
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.