The proponent proposes a seniors housing development at 2-32 Junction Street, Forest Lodge, in the City of Sydney. It would include a residential aged care facility with 10 beds and 71 independent living units, with communal spaces and landscaping. It would also include a publicly accessible open space expanding the existing Larkin Street Reserve. No capital investment is stated.
The environmental impact statement (EIS) is dated 19 Aug 2025. It drew 54 submissions: 45 objecting, 4 supporting and 5 commenting. The proponent responded to submissions in January 2026 and sent an amendment report in August 2026. The department asked for more information several times between March 2026 and November 2026, and the case is now at the More Information Required stage. Next, the department continues its assessment, then makes a recommendation and a decision.
- Independent living units
- 71 dwellingsPortal page
- Residential aged care beds
- 10 bedsPortal page
- Submissions
- 54 submissionsPortal page
The department's description
Seniors living development with a residential aged care facility including 10 beds as well as 71 independent living units. The proposal also includes a publicly accessible open space expanding on the existing Larkin Street Reserve.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
54 submissions: 51 from the public, 2 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
124 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition1
EIS46
- App 10_Visual Impact Assessment
- App 11_CPTED Report
- App 12_Arboricultural Impact Assessment
- App 14_ESD Report
- App 16_BASIX Report and Cert
- App 17_Transport Impact Assessment
- App 18_Connecting to Country
- App 19_Public Benefit Offer
- App 1_SEARs
- App 20_BDAR Waiver Request
- App 21_ BDAR Waiver letter and determination
- App 22_Noise and Vibration Assessment
- App 23_Geotech
- App 24_Acid Sulphate
- App 25_Water Mgt Plan
- App 26_Flood Impact Assessment
- App 27_Detailed Site Investigation
- App 28_Remediation Action Plan
- App 29_Waste Management Plan
- App 2_Survey
- App 3 EDC Cover Report
- App 30_Operational Waste Mgt Plan
- App 31_Hazardous Materials Register
- App 32_ACHAR Redacted
- App 33_Heritage Impact & Archaeological
- App 34_Heritage Impact Statement
- App 35_CMP
- App 36_Social Impact Assessment
- App 37_Infrastructure
- App 38_Engagement Report
- App 39_Clause 4.6 - Parking Spaces
- App 40_Clause 4.6 – FSR
- App 41_Clause 4.6 Accessible Parking
- App 4_Architectural Plans
- App 5_ Architectural Design Statement
- App 6_Public Art Strategy
- App 7_BCA Capability Statement
- App 8_Access Design Report
- App 9_Pedestrian Wind Study
- App A - SEARs Compliance Table
- App B - Statutory Compliance Table
- App C- Community Engagement Table
- App D - Draft Consolidated Mitigation Measures
- App13_Landscape Design Report
- App15_Net Zero Statement
- EIS
Response to Submissions30
- D1. Revised Arch Plans resized
- D10. Updated Transport Impact Assessment
- D11. Public Art Strategy Response Letter
- D12. Updated Public Art Strategy
- D13. Statement of Heritage Impact -updated
- D14. Heritage Response -Stone Retaining Wall
- D15. Structural Response -Stone Retaining Wall
- D16. Archaeology RTS Response - updated
- D17. VIA Response letter
- D18 - Updated VIA resized
- D19. Acoustic Response Letter
- D2.Architecture response letter
- D20. Updated Acoustic Assessment
- D21.Mechanical Rooftop Plant Response letter
- D22. Geotech Response Letter
- D23. Updated DSI resized
- D24. Soil Sampling Report
- D25 Updated RAP resized
- D26. RAP Accredited Auditor
- D27. Updated OWMP
- D28 - Public Benefit Offer
- D3.Updated Landscape Report
- D4.Landscaping Response letter
- D5. Updated Water Mgt Plan resized
- D6.Civil Response Letter
- D7. Updated Flood Impact Assessment resized
- D8. Flood Response letter
- D9. Transport Response Letter
- Request RTS Letter2012954
- WTJ24-213- Response to Submission Forest Lodge - 28.01.2026
Agency Advice23
- Ausgrid advice on EIS Oct 2025
- CPHR advice RTS Feb 2026
- CPHR advice on EIS Oct 2025
- CPHR advice on RFI May 2026
- CoS submission RTS Feb 2026
- CoS submission on EIS Oct 2025
- CoS submission on RFI May 2026
- CoS submission on RFI2 Sept 2026
- DCCEEW Water advice RTS Feb 2026
- DCCEEW Water advice on EIS Oct 2025
- FRNSW advice on EIS Sept 2025
- HNSW ACH advice RTS Feb 2026
- HNSW ACH advice on EIS Sept 2025
- HNSW advice on RTS Feb 2026
- Heritage advice on EIS Nov 2025
- MCEF advice on RFI2 Sept 2026
- NSW SES advice RTS Feb 2026
- NSW SES advice on EIS Oct 2025
- NSW SES advice on RFI May 2026
- NSW SES advice on RFI2 Sept 2026
- Sydney Metro advice on EIS Oct 2025
- Sydney Water advice on EIS Oct 2025
- TfNSW advice on EIS Oct 2025
Additional Information21
- August 2026 - Access Assessment
- August 2026 - Architectural Plans
- August 2026 - Architectural Response
- August 2026 - BCA Report
- August 2026 - Back up battery options review - Neuron
- August 2026 - Civil Response
- August 2026 - FIRA & Emergency Response Plan
- August 2026 - Forest Lodge - Amendment Report
- August 2026 - Retirement village operator opinion
- August 2026 - Structural Statement
- August 2026 - Transport Impact Assessment
- May 2026 - Attachment 1 Flood Response
- May 2026 - Attachment 2 Updated FIRA
- May 2026 - Attachment 3 - Flood Risk Management Advice
- May 2026 - Attachment 4 - Stormwater Response
- May 2026 - Attachment 5 E-LAB ESD STATEMENT
- May 2026 - Attachment 6 – Updated Archaeological Report
- May 2026 - Forest Lodge RFI Response
- NOV 2026 - Request for Additional Information
- Request for Additional Information Forest Lodge March 2026
- Request for Additional Information June 2026
What's near it
Where it is
- Suburb
- Camperdown
- Council area
- Sydney
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.