On the map
State significant development

Forest Glen Solar Farm

Decided: approved on 28 Feb 2023Energy: solarNeighbourhood scale

Where it is in the process

Approved on 28 Feb 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination28 Feb 2023 (done)
  9. Approved28 Feb 2023

What it proposes

The department's description

Development of a 90 MW solar farm and associated infrastructure, including battery storage facility.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

2 submissions: 2 from the public

Object2
Support0
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Forest Glen Solar Farm Modification 3SSD-9451258-Mod-3

Decided: approved on 31 Jul 2025 by the department (director)

Increase in the BESS capacity from 25MW one hour capacity to a 90MW two-hour capacity.

Its 16 documents

16 documents in 5 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice7

See the 7 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Forest Glen Solar Farm - Modification 2SSD-9451258-Mod-2

Decided: approved on 8 Apr 2025 by the department (director)

Seeks a minor increase in the approved development footprint to enable the use and sealing of an internal private access road.

Its 6 documents

6 documents in 3 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 1 - Increase development footprintSSD-9451258-Mod-1

Decided: approved on 4 Oct 2024 by the department (director)

Increase to development footprint area of impact by 0.42ha to reflect the final Delroy Road upgrade design. Modification also addresses changes to the substation and switching area location contained within the original development footprint.

Its 32 documents

32 documents in 6 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Amendments9

See the 9 documents on the Planning Portal

Additional Information15

See the 15 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.