Decided: approved on 13 May 2024Energy: otherNeighbourhood scale

Where it is in the process

Approved on 13 May 2024

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination13 May 2024 (done)
  9. Approved13 May 2024

What it proposes

The department's description

60 MW gas fired power station, hydrogen generation plant and 2.5 km and 500 m gas pipelines. https://www.ipcn.nsw.gov.au/cases/2024/03/dubbo-firming-power-station

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

12 submissions: 11 from the public and 1 from organisations

Object12
Support0
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

MOD 1 - Increased Generation CapacitySSD-28088034-Mod-1

Under way: at assessment · 6 submissions

Increase in generation capacity from 64 MW to 180 MW and introduction of reciprocating engines and additional land for gas pipeline connection

Its 26 documents

26 documents in 6 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application8

See the 8 documents on the Planning Portal

Response to Submissions7

See the 7 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information7

See the 7 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.