State significant development

Eastern Creek Lot 3 Outlet Centre Detailed Design

Decided: approved on 19 Feb 2024Commercial and retail

Where it is in the process

Approved on 19 Feb 2024

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination19 Feb 2024 (done)
  9. Approved19 Feb 2024

What it proposes

The department's description

Construction of 'Phase A' of the retail outlet centre on Lot 3 of the Eastern Creek Quarter.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 1 from the public, 5 from organisations and 1 from public authorities

Object3
Support1
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Eastern Creek Lot 3 Outlet Centre MOD 3SSD-31515622-Mod-3

Decided: approved on 22 Oct 2025 by the department (team leader)

The modification seeks to reconfigure electric vehicle (EV) charging spaces on site.

Its 8 documents

8 documents in 3 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Eastern Creen Lot 3 Outlet Centre - Mod 2SSD-31515622-Mod-2

Decided: approved on 30 Jul 2025 by the department (team leader)

The modification seeks the conversion of all the approved kiosks and one regular tenancy from retail outlet premises to food and drink premises.

Its 13 documents

13 documents in 5 folders, each on the NSW Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Eastern Creek Outlet Stage 2 Mod 1 Detailed DesignSSD-31515622-Mod-1

Decided: approved on 20 Sep 2024 by the department (team leader)

Correction Condition B43 relating to the M7 cycleway connection to align with the agreement between the Applicant and Council.

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.