On the map
State significant development

Dinawan Wind Farm

A 200-turbine wind farm near Jerilderie

Under way: at assessmentEnergy: windRegional scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its EIS - Main Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 200-turbine wind farm near Jerilderie

The proponent proposes a wind farm of up to 200 turbines, each up to 280 m tall to the blade tip, with a generation capacity of up to about 1,200 MW. It would sit on a project area of about 39,061 ha off McLennons Bore Road, between Coleambally and Jerilderie, in the Murrumbidgee and Edward River council areas. Ground disturbance would cover about 1,339 ha. Construction would need about 600 workers at peak and operation up to 50 full-time staff. No capital investment is stated.

The environmental impact statement (EIS), dated June 2024, was exhibited and drew 88 submissions: 86 objecting and 2 commenting. The proponent has amended the project twice. The department asked for more information in July 2026, and the case is at that stage. Next, the proponent responds, the department assesses the project and a decision follows.

Maximum wind turbines
200 turbinesEIS - Main Report
Generation capacity
1,200 MWEIS - Main Report
Maximum turbine height to blade tip
280 mEIS - Main Report
Project area
39,061 haEIS - Main Report
Development footprint
1,339 haEIS - Main Report
Peak construction personnel
600 personnelEIS - Main Report
Operational full-time employees
50 jobsEIS - Main Report

The department's description

Construction and operation of a wind farm with up to 200 wind turbines and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

88 submissions: 81 from the public and 7 from organisations

Object86
Support0
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

129 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs2
SEARs18
EIS23
Response to Submissions2
Agency Advice44
Amendments32
Additional Information7

What's near it

Where it is

Suburb
Argoon
Council areas
Murrumbidgee, Edward River

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.