On the map
State significant development

Dinawan Solar Farm

An 800 MW solar farm and battery near Jerilderie

Decided: approved on 2 Apr 2026Energy: solarRegional scale

Where it is in the process

Approved on 2 Apr 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination2 Apr 2026 (done)
  9. Approved2 Apr 2026

What it proposes

AI summary. Written from this project's page and its Development Consent and Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

An 800 MW solar farm and battery near Jerilderie

The project is a solar farm with a generating capacity of 800 MW and a lithium-ion battery of up to 356 MW and 1,574 MWh, about halfway between Coleambally and Jerilderie in the Murrumbidgee council area. The site is 3,257 ha, with a development footprint of about 1,7 ha as printed in the report. The department gives an investment value of $1,348.3 million.

The environmental impact statement (EIS) was exhibited from 17 Nov to 18 Dec, and the case drew 82 submissions, all objecting. The proponent amended the project twice, in September 2024 and November 2025. The department's assessment report of December 2025 found it approvable subject to conditions. The Independent Planning Commission approved it on 2 Apr 2026. Next, the proponent must meet the consent's conditions, including a voluntary planning agreement with the council before construction.

Generating capacity
800 MWAssessment Report
Battery storage capacity
1,574 MWhDevelopment Consent
Battery power limit
356 MWDevelopment Consent
Site area
3,257 haAssessment Report
Capital investment
$1.35bnAssessment Report
Heavy vehicle movements a day in construction
167 movementsDevelopment Consent
Submissions objecting
82 submissionsPortal page

The department's description

Development of a 800 MW solar farm, associated infrastructure and battery storage.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

82 submissions: 79 from the public and 3 from organisations

Object82
Support0
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

102 documents in 10 folders, each on the NSW Planning Portal

Request for SEARs3
SEARs14
EIS17
Exhibition1
Response to Submissions2
Agency Advice33
Amendments17
Additional Information10
Recommendation3
Determination2

What's near it

Where it is

Suburb
Jerilderie
Council area
Murrumbidgee

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.