On the map
State significant development

Currabubula Quarry Expansion Project

Expansion of the Currabubula Quarry to 750,000 tonnes a year

Under way: at prepare eisQuarriesDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Expansion of the Currabubula Quarry to 750,000 tonnes a year

The proponent proposes to expand the existing Currabubula Quarry, a hard rock andesite quarry at 3716 Werris Creek Road, about 28 km south-west of Tamworth in the Liverpool Plains Shire. It would extend the extraction area, open a new pit, raise production from the approved 400,000 tonnes a year to 750,000 tonnes a year and extend the quarry's life by up to 30 years. The quarry now covers about 22.5 ha of a 556 ha site. No capital investment or job numbers are stated.

The proponent's scoping report is dated December 2024, and the Secretary's environmental assessment requirements (SEARs) were issued on 28 Feb 2025. The proponent is now preparing an environmental impact statement (EIS). Next, the EIS would be exhibited and the public could make submissions. There are no submissions yet. The department would then assess the project and decide it.

Proposed production rate
750,000 tonnes a yearScoping Report
Currently approved production rate
400,000 tonnes a yearScoping Report
Extension of quarry life
30 yearsScoping Report
Site area
556 haScoping Report
Existing quarry area
22.5 haScoping Report

The department's description

Extension of the existing quarry extraction area, establishing a new pit, increasing the rate of production to 750,000 tonnes per annum, and extending the life of the quarry by up to an additional 30 years.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.