On the map
State significant development

Corowa BESS

A 100 MW battery at 275 Whitehead Street, Corowa

Under way: at assessmentEnergy: batteriesDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Corowa BESS - EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW battery at 275 Whitehead Street, Corowa

The proponent proposes to build, operate and later decommission a battery energy storage system with a capacity of 100 MW and 200 MWh, with associated infrastructure, at 275 Whitehead Street, Corowa, in the Federation Council area. The site is next to the existing Corowa Solar Farm and the Corowa substation. No capital investment, number of jobs or site area is stated.

The environmental impact statement (EIS) was prepared in March 2026 and exhibited, with a notice dated 15 Apr 2026. It drew 9 submissions: 4 objecting, 4 supporting and 1 commenting. The proponent has responded to submissions. The case is now at the stage where the department has asked for more information. Next, the department assesses the project, with advice from other agencies, and a decision follows.

Battery power capacity
100 MWPortal page
Battery storage capacity
200 MWhPortal page

The department's description

Construction, operation, and decommissioning of a battery energy storage system with a capacity of 100 MW / 200 MWh, and associated infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 8 from the public and 1 from organisations

Object4
Support4
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

56 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs1
SEARs1
EIS18
Response to Submissions6
Agency Advice27
Additional Information2

What's near it

Where it is

Suburb
Corowa
Council area
Federation

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.