Approved on 18 Apr 2016

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination18 Apr 2016 (done)
  9. Approved18 Apr 2016

What it proposes

The portal gives no description.

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 2 from the public and 7 from organisations

Object1
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Modification 4 Mod 4 - 2 year extensionSSD-7036-Mod-4

Decided: approved on 30 Jun 2023 by the department (director)

Extension of the project life for two years

Its 7 documents

7 documents in 5 folders, each on the NSW Planning Portal

SEARs1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Coraki Quarry MOD 3 - Processing Plant LocationSSD-7036-Mod-3

Decided: approved on 13 May 2019 by the department (director)

The proposed modification seeks to amend the approved quarry plan to reflect the as constructed location of the processing plant.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Coraki Quarry MOD 2 - Coraki QuarrySSD-7036-MOD-2

Decided: approved on 6 Jun 2017 by the department (executive director) · 1 submission

/

Its 15 documents

Its page on the Planning Portal

Coraki Quarry MOD 1 - Coraki QuarrySSD-7036-MOD-1

Decided: approved on 19 Oct 2016 by the department (executive director)

/

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Recommendation3

See the 3 documents on the Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.