State significant development

Concrush Resource Recovery Facility Expansion

Decided: approved on 27 Mar 2020Waste

Where it is in the process

Approved on 27 Mar 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination27 Mar 2020 (done)
  9. Approved27 Mar 2020

What it proposes

The department's description

Concrush is seeking to increase the processing capacity of the existing facility from 108,000 to 250,000 tonnes per annum, store up to 150,000 tonnes of waste at any one time and establish a retail business for landscaping materials and supplies.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

35 submissions: 18 from the public and 17 from organisations

Object15
Support2
Comment18

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Concrush RRF MOD 1 – Layout and Annual LimitsSSD-8753-Mod-1

Decided: approved on 19 Dec 2025 by the department (director) · 7 submissions

seeking to modify the approved capacity and storage volumes, operational hours and site layout

Its 27 documents

27 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Agency Advice14

See the 14 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.