A 100,000 tonne a year CO2 processing plant at Bomaderry

Under way: at assessmentIndustry and warehousesNeighbourhood scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100,000 tonne a year CO2 processing plant at Bomaderry

The proponent proposes a chemical manufacturing plant on Bolong Road, Bomaderry, in the Shoalhaven City Council area. It would process up to 100,000 tonnes a year of CO2-rich gas, a by-product of ethanol production at the neighbouring Shoalhaven Starches site, into high purity liquid CO2 for food and beverage uses. The project includes a pipeline, plant and equipment and storage tanks. The site is zoned E4 General Industrial and RU1 Primary Production, and the pipeline section crosses the RU1 land, where it is prohibited. No capital investment or job numbers are stated.

The environmental impact statement (EIS) was exhibited and drew 5 submissions: 1 objecting, 1 supporting and 3 commenting. The proponent has since responded to submissions, and the department has requested more information. Next, the department continues its assessment with advice from other agencies, and the Minister decides.

Production capacity
100,000 tonnes a yearPortal page
Public submissions
5 submissionsPortal page

The department's description

Construction and operation of CO2 processing plant with production capacity of 100,000 tonnes per annum of food grade CO2 including CO2 pipeline, plant and equipment and storage tanks.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

5 submissions: 3 from the public, 1 from organisations and 1 from public authorities

Object1
Support1
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

66 documents in 8 folders, each on the NSW Planning Portal

Early Consultation2
Notice of Exhibition1
Request for SEARs1
SEARs2
EIS26
Response to Submissions16
Agency Advice17
Additional Information1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.