CO2 Processing Plant, Bomaderry
A 100,000 tonne a year CO2 processing plant at Bomaderry
Where it is in the process
At assessment
What it proposes
AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 100,000 tonne a year CO2 processing plant at Bomaderry
The proponent proposes a chemical manufacturing plant on Bolong Road, Bomaderry, in the Shoalhaven City Council area. It would process up to 100,000 tonnes a year of CO2-rich gas, a by-product of ethanol production at the neighbouring Shoalhaven Starches site, into high purity liquid CO2 for food and beverage uses. The project includes a pipeline, plant and equipment and storage tanks. The site is zoned E4 General Industrial and RU1 Primary Production, and the pipeline section crosses the RU1 land, where it is prohibited. No capital investment or job numbers are stated.
The environmental impact statement (EIS) was exhibited and drew 5 submissions: 1 objecting, 1 supporting and 3 commenting. The proponent has since responded to submissions, and the department has requested more information. Next, the department continues its assessment with advice from other agencies, and the Minister decides.
- Production capacity
- 100,000 tonnes a yearPortal page
- Public submissions
- 5 submissionsPortal page
The department's description
Construction and operation of CO2 processing plant with production capacity of 100,000 tonnes per annum of food grade CO2 including CO2 pipeline, plant and equipment and storage tanks.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
5 submissions: 3 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
66 documents in 8 folders, each on the NSW Planning Portal
Early Consultation2
Notice of Exhibition1
Request for SEARs1
EIS26
- Appendix 1 - SEARs
- Appendix 10 - Geotechnical Assessment
- Appendix 11 - Hazard and Risk Assessment
- Appendix 12 - Infrastructure Requirements Report_
- Appendix 13 - Noise and Vibration Assessment
- Appendix 14 - Non-Aborignal Heritage Report
- Appendix 15 - Social Impact Assessment_
- Appendix 16 - Stormwater Management Plan and Addendum
- Appendix 17 - Transport Assessment
- Appendix 18 - Visual Impact Assessment
- Appendix 19 - Site Plans
- Appendix 2 - Aboriginal Cultural Heritage Assessment Public
- Appendix 20 - Waste Report
- Appendix 21 - Contamination Assessment
- Appendix 22 - Engagement Report
- Appendix 23 - Landscape Plan
- Appendix 3 - Air Quality and Odour Assessment_
- Appendix 4 - Arborist Report
- Appendix 5 - Biodiversity Development Assessment Report
- Appendix 6 - Ecologically Sustainability Report
- Appendix 7 - Bushfire Assessment Report
- Appendix 9 - Flood Impact Risk Assessment
- Application_20260522034107
- EDC Report - Public
- ESD Report
- Environmental Impact Statement
Response to Submissions16
- Attachment A - Amended Waste Assessment
- Attachment B - Environmental Noise Impact Assessment
- Attachment C - Construction Noise Management Plan
- Attachment D -Amended AQIA
- Attachment E - Addendum FIRA
- Attachment F - Site Plan A11
- Attachment G - Floor Plans Elevations and Sections
- Attachment H - Updated Sheet - C450
- Attachment H - Updated Sheet - C453
- Attachment H - Updated Sheet - C454
- Attachment I - Emissions Monitoring Advice
- Attachment J - Aquifer Interference Policy Review
- Attachment K - ACHA Public
- EIS - DPHI additional comments 14.08.26
- Request RTS Letter
- Response to Submissions - 2026-9-3
Agency Advice17
- CPHR - Advice on EIS
- DCA Water - Advice on EIS
- DCCEEW MCEF - Advice on EIS
- Development Coordination Authority - Advice on Submissions Report
- EPA - Advice on EIS
- EPA - Advice on Submissions Report
- FRNSW - Advice on EIS
- Heritage NSW (Aboriginal) - Advice on EIS
- Heritage NSW - Advice on EIS
- MCEF - Advice on Submissions Report
- NSW RFS - Advice on EIS
- SafeWork NSW - Advice on EIS
- SafeWork NSW - Advice on Submissions Report
- Shoalhaven City Council - Advice on EIS
- Shoalhaven City Council - Advice on Submissions Report
- TfNSW - Advice on EIS
- TfNSW - Advice on Submissions Report
Additional Information1
What's near it
Where it is
- Suburb
- Bomaderry
- Council area
- Shoalhaven
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.