Approved on 21 Dec 2007

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination21 Dec 2007 (done)
  10. Approved21 Dec 2007

What it proposes

The portal gives no description.

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

12 documents in 4 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Request for DGRS1

See the document on the Planning Portal

EIS6

See the 6 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.