On the map
State significant development

Central Sydney Industrial Estate and Downer Sustainable Road Resource Centre

Decided: approved on 31 Jan 2021Waste

Where it is in the process

Approved on 31 Jan 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination31 Jan 2021 (done)
  9. Approved31 Jan 2021

What it proposes

The department's description

Subdivision and infrastructure works to create a new 35 hectare Central Sydney Industrial Estate; and

Stage 1 works for the Development and operation of Downer’s Sustainable Road Resource Centre.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

12 submissions: 1 from the public, 1 from organisations and 10 from public authorities

Object2
Support1
Comment9

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

5 changes to the project after its decision, each assessed as a case of its own, newest first.

Central Sydney Industrial Estate MOD 5 - Subdivision and accessSSD-10459-Mod-5

Under way: at assessment

Modification to subdivide the residual land into two separate lots, finalise the creation of Lot 64, create a new driveway access with associated services, and landscaping along the new access road.

Its 12 documents

12 documents in 3 folders, each on the NSW Planning Portal

Early Consultation3

See the 3 documents on the Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 4 - DSRRC throughput increaseSSD-10459-Mod-4

Under way: at assessment

Downer proposes to modify the consent to enable an increase in annual RAP processing from 250,000 to 375,000 tpa.

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 3 - Changes to Reconomy Facility and additional waste inputSSD-10459-Mod-3

Under way: at assessment

Modifying the Reconomy facility to enable the reuse of waste in the asphalt making process and reduce the amount of waste bound for landfill. Additionally, modification is proposed to increase the variety of input recycled waste materials.

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Its page on the Planning Portal

Central Sydney Estate MOD 2 - Drainage and SubdivisionSSD-10459-Mod-2

Decided: approved on 2 Aug 2023 by the department (team leader)

Modification to subdivide unused land as part of the Central Sydney Industrial Estate Stage 1B and adjust the location of the drainage outlet.

Its 12 documents

12 documents in 6 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Post-determination Notices1

See the document on the Planning Portal

Its page on the Planning Portal

Central Sydney Estate MOD 1 - Lot DrainageSSD-10459-Mod-1

Decided: approved on 19 Nov 2021 by the department (director)

Amendments to lot drainage arrangements for CSIE

Its 9 documents

9 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.