The Children's Hospital at Westmead - Paediatric Services Building

Decided: approved on 17 Dec 2021Health

Where it is in the process

Approved on 17 Dec 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination17 Dec 2021 (done)
  9. Approved17 Dec 2021

What it proposes

The department's description

Construction of a new 14 level (including basement) Paediatric Services Building with rooftop helipad, ancillary works to adjoining buildings, a pedestrian canopy link, forecourt works, landscaping and tree removal.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

12 submissions: 2 from the public, 1 from organisations and 9 from public authorities

Object1
Support0
Comment11

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

CHW PSB MOD 2 - Design changesSSD-10349252-Mod-2

Decided: approved on 30 Jan 2024 by the department (team leader)

Changes to the central courtyards, rooftop landscaping, glazing, external plant area, pylon signage design and a reduction in the number of building identification signs.

Its 11 documents

11 documents in 3 folders, each on the NSW Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

CHW PSB MOD 1 - Design refinementsSSD-10349252-Mod-1

Decided: approved on 12 Dec 2022 by the department (team leader)

Minor design refinements including changes to the building footprint, and internal layouts that are as the result of ongoing design development, minor changes to car parking and construction of a secondary pedestrian access ramp.

Its 18 documents

18 documents in 4 folders, each on the NSW Planning Portal

Modification Application12

See the 12 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.