Capital Solar Farm
Where it is in the process
Approved on 21 Dec 2010
What it proposes
The department's description
Development of a 50MW solar farm, linked to the Capital Wind Farm substation.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Modifications
2 changes to the project after its decision, each assessed as a case of its own, newest first.
Capital Solar MOD 2 - Capital SolarMP10_0121-Mod-2
Allowing tracking photovoltaic panels to be installed at the projects.
Its 7 documents
7 documents in 4 folders, each on the NSW Planning Portal
Application1
Recommendation1
Determination2
MOD 1 - Deletion of Conditions of ConsentMP10_0121-Mod-1
Deletion of Conditions of Consent F2 and F3 to remove need for operational stage noise monitoring, given that the solar farm will have no moving parts or noise sources other than occassional light vehicle movement.
Its 5 documents
5 documents in 2 folders, each on the NSW Planning Portal
Application2
Determination3
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
21 documents in 5 folders, each on the NSW Planning Portal
Application1
Response to Submissions1
Determination3
What's near it
Where it is
- Suburb
- Lake George
- Council area
- Queanbeyan-Palerang Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.