Blind Creek Solar Farm
A 350 MW solar farm and battery near Bungendore
Where it is in the process
Approved on 28 Jul 2023
What it proposes
AI summary. Written from this project's page and its Instrument of Determination and Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 350 MW solar farm and battery near Bungendore
Blind Creek Solar Farm Pty Ltd proposed a solar farm with a generating capacity of 350 MW and a battery of up to 300 MW / 600 MWh. It is at 114 Currandooley Road, Bungendore, about 7 km north of Bungendore in the Queanbeyan-Palerang Regional Council area. The site is 1,026 ha, with a development footprint of 682.5 ha. The capital investment is $503.7 million, with up to 300 construction jobs at peak and up to 5 operational jobs.
The environmental impact statement (EIS) was exhibited from 7 Jun 2022 to 7 Jul 2022. The department received 45 public submissions (4 objecting, 38 supporting, 3 commenting), and the portal counts 46 in all. The proponent amended the project in December 2022, reducing its footprint. The department's Director, Energy Assessments, approved it on 28 Jul 2023 as the Minister's delegate, with conditions. Next, the proponent must meet those conditions, including road upgrades, before construction.
- Capital investment
- $503.7MAssessment Report
- Solar generating capacity
- 350 MWAssessment Report
- Battery power capacity
- 300 MWAssessment Report
- Battery storage capacity
- 600 MWhAssessment Report
- Construction jobs at peak
- 300 jobsAssessment Report
- Operational jobs
- 5 jobsAssessment Report
- Site area
- 1,026 haAssessment Report
- Development footprint
- 682.5 haAssessment Report
The department's description
Development of a 350 MW solar farm with battery storage and associated infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
46 submissions: 40 from the public, 5 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
89 documents in 11 folders, each on the NSW Planning Portal
Request for SEARs1
EIS15
- Appendix A - SEARs
- Appendix B - Proposed Maps and Drawings
- Appendix D - Consultation
- Appendix E - Visual Impact Assessment
- Appendix F - Reflective Glare Assessment
- Appendix G - Biodiversity Development Assessment Report
- Appendix H - Aboriginal Cultural Heritage Assessment
- Appendix I - Hydrological and Hydraulic Analysis
- Appendix J - Noise and Vibration Assessment
- Appendix K - Traffic Impact Assessment
- Appendix L - Statement Of Heritage Impact
- Appendix M - Social Impact Assessment
- Appendix N - Preliminary Hazard Analysis
- Appendix O - Background Search Results
- EIS
Response to Submissions18
- AR Appendix A Updated Project Decription
- AR Appendix D Engagement
- AR Appendix E.1 Updated BDAR
- AR Appendix E.2 Updated VIA
- AR Appendix E.3 Glint and glare memo
- AR Appendix E.4 TIA and BAR treatment
- AR Appendix E.5 Disturbance Report - Tarago Road
- AR Appendix E.6 Addendum ACHA
- AR Appendix E.7 Addendum Noise Report
- Amendment Report
- Appendix C Addendum ACHAR
- Appendix D Crown Lands Consultation
- Appendix E Glint & Glare Assessment
- Appendix F Updated BDAR
- Appendix G Updated VIA
- Appendix I Updated BAR treatment
- Appendix I Updated TIA
- Submissions Report
Agency Advice18
- BCD RTS comments
- Biodiversity, Conservation and Science Directorate (BCD)
- Crown Lands
- Crown Lands RTS comments
- DPE Water
- DPE Water RTS comments
- DPI Agriculture
- DPI Fisheries
- DPI Fisheries RTS comments
- EPA
- FRNSW RTS comments
- Fire and Rescue
- HNSW ACH RTS comments
- Heritage NSW ACH
- MEG GSNSW
- MEG RTS comments
- TfNSW RTS comments
- WaterNSW
Additional Information6
Recommendation2
Management Plans and Strategies21
- Accommodation and Employment Strategy
- Accommodation and Employment Strategy Approval
- Biodiversity Management Plan
- Biodiversity Management Plan Approval
- Environmental Management Strategy
- Environmental Management Strategy Approval
- Fire Safety Study
- Fire Safety Study Approval
- Heritage Management Plan
- Heritage Management Plan Approval
- Landscaping Plan
- Landscaping Plan Approval
- TMP Staging Approval
- Traffic Management Plan
- Traffic Management Plan
- Traffic Management Plan
- Traffic Management Plan Approval
- Traffic Management Plan Approval
- Traffic Management Plan Stage 1
- Traffic Management Plan Stage 1 Approval
- Traffic Management Plan Stage 1 Approval
What's near it
Where it is
- Suburb
- Bungendore
- Council area
- Queanbeyan-Palerang Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.