Campbelltown Arts Centre Expansion
Expansion of the Campbelltown Arts Centre, Art Gallery Road
Where it is in the process
At assessment
What it proposes
AI summary. Written from this project's page and its Environmental Impact Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Expansion of the Campbelltown Arts Centre, Art Gallery Road
Campbelltown City Council proposes to expand and renew the Campbelltown Arts Centre at 1 Art Gallery Road, Campbelltown, on a site of about 18,877 m². The work includes demolishing parts of the existing buildings and adding a new 350 seat theatre, expanded galleries, workshop and rehearsal spaces, artists' residences, and a café, retail and conference space. Car parking and landscaping would also be expanded. The environmental impact statement (EIS) forecasts a peak of 120 construction jobs and 34 operational jobs. No capital investment is stated.
The Secretary's environmental assessment requirements (SEARs) were issued on 7 Aug 2024. The EIS is dated 1 May 2026 and was exhibited, with a notice dated 21 May 2026, drawing 4 submissions: 3 supporting and 1 commenting. The proponent has since responded to submissions. The case is now at the More Information Required stage. Next, the proponent provides that information and the department continues its assessment before a decision.
- Site area
- 18,877 m²Environmental Impact Statement
- Theatre seats
- 350 seatsEnvironmental Impact Statement
- Peak construction jobs
- 120 jobsEnvironmental Impact Statement
- Operational jobs
- 34 jobsEnvironmental Impact Statement
The department's description
Expansion of the Campbelltown Arts Centre.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
4 submissions: 2 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
78 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs3
SEARs2
EIS42
- A - Architectural Drawings
- AA - Groundwater and Surface Water Assessment
- B – SEARs Compliance Table
- BB - Salinity Management Plan
- C - Architectural Design Report
- D - Survey Plan
- DD - Acid Sulfate Soil Review
- E - Preliminary CTMP
- E - Preliminary Green Travel Plan
- E - Transport and Accessibility Impact Assessment
- EE - Arboricultural Impact Assessment
- Environmental Impact Statement
- F - Landscape Drawings
- FF - Lighting Report
- G - Statutory Compliance Table
- GG - Operational Waste Management Plan
- H - BDAR waiver
- HH - CDWMP
- I - Detailed Site Investigation
- II - Destructive Hazardous Materials Assessment
- J - Infrastructure and Utilities Report
- JJ - Fire Engineering Support Letter
- K - ESD Report and Net Zero Statement
- K - NABERS
- K - Net Zero Statement
- KK - BCA Capability Statement
- L - Flood Impact Risk Assessment
- LL - Accessibility Capability Statement
- M - Geotechnical Report
- N - Engagement Outcomes Report
- O - Community Engagement Table
- P - Aboriginal Cultural Heritage Assessment Report
- Q - Mitigation Measures Table
- R - Flood Emergency Response Plan
- S - Noise and Vibration Report
- T - Social Impact Assessment
- U - CPTED Report
- V - Heritage Impact Statement
- W - Historical Archaeological Assessment
- X - Integrated Water Management Plan
- Y - Hydraulic Services IWMP
- Z - Qualitative Wind Assessment
Response to Submissions21
- Appendix A - Architectual Response Letter
- Appendix B - Updated Site Plan
- Appendix C - Updated Demolition Plans
- Appendix D - Council CPTED Response Letter
- Appendix E - Electrical Response Letter
- Appendix F - Flooding Response Letter
- Appendix G - Updated Flood Emergency Response Plan
- Appendix H - Updated Flood Impact and Risk Assessment
- Appendix I - Traffic Response Letter
- Appendix J - Updated Transport Impact Assessment
- Appendix K - Easement Plan
- Appendix L - ASP Compliance Plans
- Appendix M - Updated Lighting Report
- Appendix N - Groundwater Impact RTS Letter
- Appendix O - Riparian Zone Letter
- Appendix P - Submissions Register
- Appendix Q - Updated Survey Plans
- Appendix R - Stantec Survey Letter
- Appendix S - Council Survey Letter
- Campbelltown Arts Centre RtS Report
- Request RTS Letter
Additional Information2
What's near it
Where it is
- Suburb
- Campbelltown
- Council area
- Campbelltown
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.