Burrows Road Multi-level Warehouse, St Peters
A two-storey warehouse at 1-3 Burrows Road, St Peters
Where it is in the process
Approved on 2 Apr 2026
What it proposes
AI summary. Written from this project's page and its SSD Assessment Report and SSD Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A two-storey warehouse at 1-3 Burrows Road, St Peters
The project is a two-storey warehouse and distribution centre at 1-3 Burrows Road, St Peters, in the City of Sydney area, on a site of 3.46 ha. It has eight tenancies and a gross floor area of 34,051 m², and would be up to 25 m high. It includes 145 car parking spaces and 48 loading docks. The department gives an estimated development cost of $206,410,000, up to 684 construction jobs and 425 operational jobs.
The application was exhibited from 18 Nov 2022 to 15 Dec 2022. The proponent amended it, cutting the height from three levels to two, and it was exhibited again from 11 Feb 2025 to 10 Mar 2025. The five submissions came from councils, agencies and organisations. The department recommended approval, and a director of the department, acting for the Minister, approved it on 2 Apr 2026, with conditions. Next, the proponent must meet those conditions, including traffic and noise management plans, before and during construction.
- Estimated development cost
- $206.4MSSD Assessment Report
- Construction jobs
- 684 jobsSSD Assessment Report
- Operational jobs
- 425 jobsSSD Assessment Report
- Gross floor area
- 34,051 m²SSD Assessment Report
- Site area
- 3.46 haSSD Assessment Report
- Maximum building height
- 25 mSSD Assessment Report
- Car parking spaces
- 145 car spacesSSD Assessment Report
- Loading docks
- 48 loading docksSSD Assessment Report
The department's description
The development involves the construction of a multi-level industrial warehouse and distribution facility development with an ancillary integrated office building, vegetation removal and landscaping works.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
5 submissions: 2 from organisations and 3 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
Burrows Road Multi-level Warehouse, St Peters - Burrows Road Multi-Level Warehouse - MOD1 Landscaping amendmentSSD-35962232-Mod-1
Correct administrative error through update of Tree Removal & Retention Plan to correspond with approved Arboricultural Impact Assessment, and correctly reference trees approved for removal.
Its 8 documents
8 documents in 3 folders, each on the NSW Planning Portal
Modification Application5
Determination2
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
205 documents in 10 folders, each on the NSW Planning Portal
Early Consultation2
Notice of Exhibition2
Request for SEARs1
SEARs2
EIS43
- Appendix AA_Remediation Action Plan
- Appendix A_SEARs Compliance Table
- Appendix BB_Site Audit Report (Interim Advice)
- Appendix B_Statutory Compliance Table
- Appendix CC_Waste Management Plan
- Appendix C_Mitigation Measures
- Appendix DD_Hazardous Materials Survey
- Appendix DD_Hazardous Materials Survey 2005
- Appendix D_Engagement Summary Table
- Appendix EE_ACHAR_Redacted
- Appendix E_QS Cost Estimate Report
- Appendix FF_Social Impact Assessment
- Appendix F_Survey Plan
- Appendix GG (1)_Utilities Report
- Appendix GG (2)_Utilities Report
- Appendix G_Architectural Drawings
- Appendix G_Architectural Drawings - Public Art Strategy
- Appendix HH Engagement Outcomes Report
- Appendix H_Design Report
- Appendix II - Clause 4.6 Variation_FSR - 1-3 Burrows Road
- Appendix I_Design Excellence Strategy
- Appendix J_Design Competition Report
- Appendix K_Design Integrity Panel Endorsement
- Appendix L_BCA Compliance
- Appendix M_Fire Safety Strategy
- Appendix N_Visual Impact Assessment
- Appendix O_Transport, Traffic & Accessibility Assessment
- Appendix P_Landscape Plans
- Appendix Q_AIA
- Appendix R_ESD Report
- Appendix S (1)_BDAR Waiver
- Appendix S (2)_BDAR Waiver
- Appendix T_Air Quality Impact Assessment
- Appendix U_Noise and Vibration Impact Assessment
- Appendix V_Geotechnical Investigation
- Appendix W (2)_Salinity Management Plan
- Appendix W_Salinty Management Plan
- Appendix X_Civil Engineering Report
- Appendix Y_Hazard Analysis
- Appendix Z (1)_Phase 1&2 Environmental Investigation
- Appendix Z (2)_Phase 1&2 Environmental Investigation
- Application_20221102062658
- Environmental Impact Statement_Final
Response to Submissions31
- Appendix A Revised Architectural Plans
- Appendix A1_Office drop-off area analysis
- Appendix A_Updated Architectural Drawings
- Appendix B Architectural Design Response Letter
- Appendix B_Landscape Drawings & Maintenance Strategy
- Appendix C Revised Landscape Plans
- Appendix C1_MUSIC Model
- Appendix C_Civil Engineering and Flooding Rpeort and Plans
- Appendix D - Noise and Vibration Impact Assessment
- Appendix D Revised Traffic Report
- Appendix E Revised Civil Engineering Plans
- Appendix E1_Air Quality Impact Memorandum
- Appendix E_Air Quality Impact Assessment
- Appendix F Revised Flood Report
- Appendix F_TMAP
- Appendix F_Vehicle Manouvering Plans
- Appendix G TfNSW Landowners Consent dated 28 May 2025
- Appendix G_BDAR Waiver Request
- Appendix H_Arboriculture Impact Assessment
- Appendix I_Remediation Action Plan
- Appendix J_Supplementary Site Investigation
- Appendix K_Site Audit Report
- Appendix L_Mitigation Measures
- Appendix M _VIA
- Appendix N_Design Integrity Panel Advice
- Appendix O_Green Stage Building v1.0 Accreditation
- Department Request RTS for Amendment Report
- Request RTS - DPE additional comments
- Request RTS Letter
- Submissions Report
- Submissions Report_1-3 Burrows Road, St Peters_SSD-35962232
Agency Advice35
- Ausgrid advice on Amendment Report
- Bayside Council - Advice on EIS
- Bayside Council - Advice on RTS
- Bayside Council response to Amendment Report
- Bayside response to RtS 26.06.2025
- CASA - advice on EIS-RTS
- CPHR response to Amendment Report
- CPHR response to RtS 11.07.25
- City of Sydney - Additional advice on EIS
- City of Sydney - Advice on EIS
- City of Sydney - Advice on RTS
- CoS response to Amendment Report 12.03.2025
- CoS response to RtS 26.06.2025
- EHG - Advice on EIS
- EHG Advice on RTS
- EPA Advice on RTS
- EPA advice on EIS
- EPA response Amendment Report
- FRNSW - Advice on EIS
- GA response to RTS 9.07.25
- HNSW ACH - Advice on EIS
- HNSW ACH advice on Amendment Report
- HNSW advice on Amendment Report
- Heritage Council NSW - Advice on EIS
- Inner West Council - Advice on EIS
- Inner West Council - advice on RTS
- Inner West Council 4.07.2025
- Inner West Council response to Amendment Report
- NSWF&R advice on Amendment Report
- SES - advice on EIS - RTS
- Sydney Airport response to Amendment Report
- Sydney Water - Advice on EIS
- TfNSW - Advice on EIS
- TfNSW - Advice on RTS
- TfNSW advice on Amendment Report
Amendments41
- 1-3 Burrows Road Amendment Report V5
- Amended Application_20241202012338
- Amendment Acceptance Letter
- Appendix A - SEARs Compliance Table
- Appendix AA - Remediation Action Plan Letter
- Appendix B - Architectural Plans
- Appendix BB - Interim Audit Advice Letter
- Appendix C - Statutory Compliance Table
- Appendix CC - Waste Management Plan
- Appendix D - Mitigation Measures
- Appendix DD - Hazardous Materials Survey
- Appendix E - Engagement Summary Table
- Appendix EE - Aboriginal Cultural Heritage
- Appendix F - Estimated Development Cost Report
- Appendix FF - Social Impact Assessment
- Appendix G - Survey Plan
- Appendix GG - Electrical and Comms
- Appendix H - Design Report
- Appendix HH - Engagement
- Appendix I - Design Excellence Strategy
- Appendix II - Response to Submissions
- Appendix J - Design Competition Report
- Appendix JJ - Section 37 Amendment Letter
- Appendix K - Design Integrity Panel Endorsement
- Appendix L - BCA Compliance Report
- Appendix M - Fire Safety Strategy
- Appendix N - Visual Impact Assessment
- Appendix O - Transport Management
- Appendix P - Landscape Plans
- Appendix Q - Arboricultural
- Appendix R - ESD Report
- Appendix S - BDAR Waiver
- Appendix T - Air Quality Report
- Appendix U - Noise Impact Assessment
- Appendix V - Geotechnical Report
- Appendix W - Soil Salinity Assessment
- Appendix W(2) - Soil Salinity Management Plan
- Appendix X - Civil Engineering and Flood Report
- Appendix Y - Hazard Analysis
- Appendix Z - Groundwater Assessment
- SSD-35962232_Section 37 Amendment Request
Additional Information45
- 1-3 Burrows Road Amendment Report
- Appendix A - SEARs Compliance Table
- Appendix AA - Remediation Action Plan Letter of Support
- Appendix B - Architectural Plans
- Appendix BB - Interim Audit Advice Letter
- Appendix C - Statutory Compliance Table
- Appendix CC - Waste Management Plan
- Appendix D - Mitigation Measures
- Appendix DD - Hazardous Materials Survey
- Appendix E - Engagement Summary Table
- Appendix EE - ACHAR Report
- Appendix FF - Social Impact Assessment
- Appendix G - Survey Plan
- Appendix GG - Electrical and Comms
- Appendix H - Design Report
- Appendix HH - Engagement
- Appendix I - Design Excellence Strategy
- Appendix II - Response to Submissions
- Appendix J - Design Competition Report
- Appendix JJ - Section 37 Amendment Letter
- Appendix K - Design Panel Endorsement
- Appendix L - BCA Compliance Report
- Appendix M - Fire Safety Strategy
- Appendix N - Visual Impact Assessment
- Appendix O - Transport Management & Accessibility Plan
- Appendix P - Landscape Plans
- Appendix Q - Arboricultural
- Appendix R - ESD Report
- Appendix S - BDAR Waiver
- Appendix T - Air Quality Report
- Appendix U - Noise Impact Assessment
- Appendix V - Geotechnical Report
- Appendix W - Soil Salinity Assessment
- Appendix W(2) - Soil Salinity Management Plan
- Appendix X - Civil Engineering and Flood Report
- Appendix Y - Hazard Analysis
- Appendix Z - Groundwater Assessment
- DPHI request for additional information 24.07.25
- RFI - Updated noise impact assessment
- RTS_Inner West_27.07.23
- Request for Additional Information
- Request for Additional Information - Agency advice
- Request for Additional Information - Visual 27 June
- Request for Additional Information May 2023
- SSD-35962232_Section 37 Amendment Request
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.