On the map
State significant development

Bogan River Solar Farm

Decided: approved on 20 Dec 2010Other

Where it is in the process

Approved on 20 Dec 2010

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination20 Dec 2010 (done)
  8. Approved20 Dec 2010

What it proposes

The department's description

Development of a 100 MW solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Bogan River Solar MOD 1 - Bogan River SolarMP10_0123-Mod-1

Decided: approved on 9 Dec 2015 by the department (director)

3 year extension to the approval lapse date, deletion of conditions regarding operational noise testing, option of installing tracking/fixed panels, refinement of land allotments, update of references and increased panel height.

Its 5 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.