On the map
State significant development

BlueScope Erskine Park Metal Coating Line 7

Decided: approved on 15 Sep 2023Industry and warehouses

Where it is in the process

Approved on 15 Sep 2023

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination15 Sep 2023 (done)
  9. Approved15 Sep 2023

What it proposes

The department's description

Construction and operation of a metal coating line with the a processing capacity of 240 kilo tonnes per annum (ktpa) of cold rolled coil including despatch building, three stacks, storage areas, office and laboratory.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 4 from the public, 2 from organisations and 1 from public authorities

Object1
Support5
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Metal Coating Line 7 MOD 2 - Tree plantingSSD-45510464-Mod-2

Decided: approved on 23 Sep 2025 by the department (team leader)

Alteration to number of trees proposed within the car park

Its 10 documents

10 documents in 4 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Metal Coating Line 7 MOD 1 - Nitrogen SystemSSD-45510464-Mod-1

Decided: approved on 4 Dec 2024 by the department (team leader)

Installation of a liquid nitrogen ASSIST system (LAS) to supply the development for metal coating process and remove the dependency on liquid nitrogen freight.

Its 15 documents

15 documents in 5 folders, each on the NSW Planning Portal

Modification Application6

See the 6 documents on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.