Barangaroo - Stage 1B Basement
Where it is in the process
Approved on 7 Mar 2017
What it proposes
The portal gives no description.
Submissions
What the public, organisations and public authorities said, counted by where they stood.
3 submissions: 1 from the public and 2 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
6 changes to the project after its decision, each assessed as a case of its own, newest first.
Barangaroo South Stage 1B Basement Mod 6SSD-6960-Mod-6
Minor design changes to the basement plans
Its 9 documents
9 documents in 5 folders, each on the NSW Planning Portal
Modification Application3
Agency Advice1
Additional Information2
Determination2
Consolidated Consent1
Barangaroo South Stage 1B Basement Mod 5SSD-6960-Mod-5
Design changes
Its 7 documents
7 documents in 3 folders, each on the NSW Planning Portal
Modification Application3
Determination3
Consolidated Consent1
Stage 1B Basement Barangaroo South MOD 4 - LayoutSSD-6960-Mod-4
Changes to the Stage 1B basement layout at Barangaroo South, adding 27.8 m² of floor area, approved by the department on 8 Mar 2021.
The department's description
Increase in non-residential Gross Floor Area within the basement from 65 m2 to 92.8 m2 and amendments to basement layout.
Its 5 documents
5 documents in 2 folders, each on the NSW Planning Portal
Modification Application2
Stage 1B Basement Barangaroo South MOD 3 - LayoutSSD-6960-Mod-3
- Increase of non-residential GFA within the basement to a total of 65m2 for shared facilities (e.g. operations manager room, security control room, utility induction room). - Minor adjustments to the basement layout.
Its 6 documents
6 documents in 3 folders, each on the NSW Planning Portal
Modification Application2
Additional Information1
Determination3
Barangaroo Stage 1B MOD 2 - Basement levelsSSD-6960-Mod-2
Adjust the levels of the basement slab to align with the Barangaroo Public Domain (SSD 7944).
Its 7 documents
7 documents in 2 folders, each on the NSW Planning Portal
Agency Advice4
Determination3
Barangaroo Stage 1B Basement Mod 1SSD-6960-MOD-1
.
Its 20 documents
20 documents in 5 folders, each on the NSW Planning Portal
Application1
Submissions2
Response to Submissions3
Determination3
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
81 documents in 8 folders, each on the NSW Planning Portal
Request for DGRS1
Application3
Submissions8
Response to Submissions22
Recommendation1
Determination3
What's near it
Where it is
- Suburb
- Barangaroo
- Council area
- Sydney
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.